CIPS Level 5 Advanced Diploma in Procurement and Supply L5M8 Dumps PDF

Page: 3 / 7
Total 88 questions

Project and Change Management Questions and Answers

Question 9

Which of the following is a type ofProject Responsibility Chart?

Options:

A.

SWOT

B.

Gantt Chart

C.

PRINCE2

D.

RACI

Question 10

What information does aCritical Path scheduleprovide to the project team?Select TWO

Options:

A.

where the project is up to in terms of delivery

B.

a realistic duration of the project

C.

the longest and shortest possible durations of the project

D.

why the project is delayed

Question 11

In a large construction project with many stakeholders, which groups would you expect to see represented on theProject Board?Select TWO

Options:

A.

Senior Employees

B.

Senior Users

C.

Senior Suppliers

D.

Senior Buyers

Question 12

Which of the following situations would be considered a‘soft’problem?

Options:

A.

a technical problem with a system

B.

a shift in culture leading to changing buying habits of customers

C.

a delivery of vital materials has been lost in transit

D.

a manager has been found guilty of bribery

Page: 3 / 7
Total 88 questions