Project and Change Management Questions and Answers

Question 17

Which of the following is aninternational standard for Social Responsibility?

Options:

A.

ISO 26000

B.

ISO 27000

C.

Social Value Act

D.

Ethical Trading Initiative

Question 18

Yes Ltd is a consultancy organisation running many projects simultaneously. Fiona, the CEO, claims that all projects should use project management software. Is this correct?

Options:

A.

yes – software will ensure projects are delivered to timescales and budgets

B.

yes – all projects require the use of software to track data

C.

no – the use of software may not be required for smaller projects

D.

no – software should never be used as a project management tool

Question 19

At what point does aproject close?

Options:

A.

when the time allocated to the project runs out

B.

when the project success criteria have been achieved

C.

when the project executive leaves

D.

when the budget has been exhausted

Question 20

TheCritical Path Method (CPM)can provide a schedule for a project and demonstrates the longest path of activities to be completed. The critical path provides the longest “path” in terms of what?

Options:

A.

the largest number of steps that need to be completed

B.

the highest number of activities that need to be completed

C.

the longest time all activities will take to complete

D.

the most complex route to complete the activities