Big Black Friday Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

H12-425_V2.0 Exam Dumps : HCIP-Data Center Facility Deployment V2.0

PDF
H12-425_V2.0 pdf
 Real Exam Questions and Answer
 Last Update: Nov 28, 2025
 Question and Answers: 55
 Compatible with all Devices
 Printable Format
 100% Pass Guaranteed
$25.5  $84.99
H12-425_V2.0 exam
PDF + Testing Engine
H12-425_V2.0 PDF + engine
 Both PDF & Practice Software
 Last Update: Nov 28, 2025
 Question and Answers: 55
 Discount Offer
 Download Free Demo
 24/7 Customer Support
$40.5  $134.99
Testing Engine
H12-425_V2.0 Engine
 Desktop Based Application
 Last Update: Nov 28, 2025
 Question and Answers: 55
 Create Multiple Test Sets
 Questions Regularly Updated
  90 Days Free Updates
  Windows and Mac Compatible
$30  $99.99

Verified By IT Certified Experts

CertsTopics.com Certified Safe Files

Up-To-Date Exam Study Material

99.5% High Success Pass Rate

100% Accurate Answers

Instant Downloads

Exam Questions And Answers PDF

Try Demo Before You Buy

Certification Exams with Helpful Questions And Answers

HCIP-Data Center Facility Deployment V2.0 Questions and Answers

Question 1

If the battery charge current limit coefficient of the UPS5000-E is set to 0.1C10, which of the following statements about this parameter is true?

Options:

A.

The maximum batten/ charge current is 0.1C10.

B.

The batten/ charge current is always 0.1C10.

C.

The battery float charge current is 0.1C10.

D.

The maximum battery charge current is 0.1C10.

Buy Now
Question 2

Three UPS5000-E-400Ks from a 2+1 parallel system. Which of the following statements about the parallel system are true?

Options:

A.

The parallel system capacity displayed on the LCD is 1200 kVA.

B.

The networkingmode is set to one-to-multiple for one UPS, and set to one-to-one for the other two UPSs.

C.

If the load is 420 kW, each of two UPSs carries 210 kW load, and the other one is standby and does not carry load.

D.

If the load is 420 kW, each of the three UPSs carries 140kW load.

Question 3

Which of the following requires a cooling tower or drycooler?

Options:

A.

Direct ventilation air conditioning system.

B.

DX air cooled air conditioner.

C.

CW air cooled air conditioner.

D.

DX water cooled air conditioner.