ISTQB Related Exams
CTAL-TM Exam
You are documenting a test methodology for your organisation and have specified that the following activities must be adopted for all future projects: 1. The design, implementation and execution of tests to mitigate the quality risks
2 Extensive use of checklists to test web page navigation
3 Exploratory test sessions to be integrated into the test schedule Consider the following test strategies:
a. Analytical test strategy
b Methodical test strategy
c. Process or standard compliant test strategy
d Reactive test strategy
e. Regression-averse test strategy
Which three of these strategies is MOST appropriate for this organisation?
Which of the following best describes the appraisal costs in the cost of quality'
SoftTech provides a core banking product to retail banks to enable their customers to process payments via the Internet and telephone banking and. as SoftTech's Test Manager, you are responsible for system testing and system integration testing of all SoftTech's products.
Your current project is to integrate SoftTech's core banking product with an existing bank's systems, which are maintained by experienced developers but poorly
documented.
A specification for the 10 interfaces to the bank's existing systems has been produced by SoftTech's development team. There is an estimating matrix for system integration testing that allows 2 man days per interface for preparation, plus 2 man days per interface for test execution. The exit criteria for the completion of system integration testing has been agreed as:
1. No open Severity 1 defects
2 No more than 10 open severity 2 and/or 3 defects
3. All interfaces tested
4. Cost estimate must not be exceeded
System integration test execution is scheduled to last 5 weeks, with week 5 reserved for regression and bug fixing only. At the end of week 3 the following test report has been produced (figures on a week by week basis, not cumulative):

B. Open severity 2 and 3 defects
c. Interface testing progress
d. Development resource for debugging
e. Available budget
SELECT ONE OPTION