Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PRINCE2 PRINCE2-Agile-Foundation Dumps

PRINCE2 Agile Foundation Exam Questions and Answers

Question 1

What should be emphasized when tailoring the PRINCE2 Progress theme?

Options:

A.

Monitoring what is being delivered

B.

Tracking time and cost

C.

Planning resources

D.

Assessing the impact of risks

Question 2

Which well-known agile method uses visualization, and controls work in progress?

Options:

A.

Scrum

B.

Lean Startup

C.

Lean

D.

Kanban

Question 3

Which statement is CORRECT with respect to the management of risk using PRINCE2 Agile?

Options:

A.

It should always be appropriate to the needs of the project

B.

It should always be addressed during the daily stand-ups

C.

It should always be carried out formally

D.

It should always be carried out informally

Question 4

What is an epic?

Options:

A.

A low-level requirement

B.

A fine-grained user story

C.

A detailed feature

D.

A high-level requirement

Question 5

When should PRINCE2 Agile be used?

Options:

A.

When a team is created to deliver a specific product

B.

When delivering an ongoing service to a customer

C.

When an established team performs product maintenance

D.

When simple requests to update a product are implemented

Question 6

What is an epic?

Options:

A.

A detailed user story with high business value

B.

The set of products handed over to the users

C.

A high-level user story that is quite broad or vague

D.

A prioritized list of requirements to be delivered in a sprint

Question 7

During which process should release planning be done for the FIRST time?

Options:

A.

Initiating a project

B.

Managing a stage boundary

C.

Managing product delivery

D.

Controlling a stage

Question 8

Which statement describes how the PRINCE2 ‘starting up a project’ process can be applied in an agile environment?

Options:

A.

PRINCE2 is predictive, but not emergent

B.

PRINCE2 is predictive and can be emergent

C.

PRINCE2 requires a lengthy start to a project

D.

PRINCE2 requires a disruptive start to a project

Question 9

Which process can take place during a release review workshop?

Options:

A.

Controlling a stage

B.

Managing product delivery

C.

Managing a stage boundary

D.

Directing a project

Question 10

Which is an advantage of using the PRINCE2 Agile behavior ‘collaboration’?

Options:

A.

It ensures that there are no surprises

B.

It allows people to provide cover for one another

C.

It uses experimentation to expand requirements

D.

It uses learning to help improve products

Question 11

Which is a purpose of the ‘managing product delivery’ process?

Options:

A.

To plan the delivery of the products before committing to significant expenditure

B.

To agree on what is required for accepting, executing and delivering project work.

C.

To establish and deliver the project communications to the wider organization

D.

To delegate day-to-day management of the project to the project manager

Question 12

Which statement about the ‘directing a project’ process is CORRECT?

Options:

A.

The project board should attend regular project progress meetings

B.

The project board should make decisions based on the Agilometer risks

C.

A project board member should fulfill the product owner role within a delivery team

D.

The project board should increase the stage-level time tolerance

Question 13

Which statement about timeboxes is CORRECT?

Options:

A.

Flow based working partitions work into timeboxes

B.

A project cannot be referred to as a timebox

C.

A timebox can contain another timebox

D.

Timeboxes should be avoided in business as usual environments