Month End Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PRINCE2-Agile-Foundation Questions Bank

PRINCE2 Agile Foundation (Version 2) Exam Questions and Answers

Question 17

Which of the following is a prioritized list of the requirements for a product?

Options:

A.

Project canvas

B.

Release map

C.

Project log

D.

Backlog

Question 18

Which is an advantage of frequent releases?

Options:

A.

Releases can be used to replace management stages

B.

A ‘one-team’ culture in the project team is encouraged

C.

Configuration management becomes less important

D.

The delivery team becomes more experienced at product handover

Question 19

Which describes the Scrum Master role in Scrum?

Options:

A.

It is authorized to run the project on a day-to-day basis on behalf of the project board

B.

It is responsible for ensuring that product backlog items are clearly expressed on the product backlog

C.

It is empowered to organize and manage its own work to create a valuable, useful increment every sprint

D.

It is servant-leadership to help everyone change their interactions to maximize the value created by the team

Question 20

In which workshop does planning for the next stage occur?

Options:

A.

Team planning workshop

B.

Release planning workshop

C.

Team retrospective workshop

D.

Progress review workshop