Question 17

Which statement describes the Kanban approach?

Options:

A.

It is used to make system improvements using visualization and by controlling work in progress

B.

It is an iterative timeboxed approach that helps teams generate value

C.

It was originally focused in creating new companies and is now used to speed up product delivery

D.

It has defined processes, products and roles used to iteratively deliver outputs using timeboxing

Question 18

Which TWO project board responsibilities are specifically assigned to the senior user?

1) Demonstrating the achievement of benefits.

2) Specifying the needs of those impacted by the outputs.

3) Balancing business, user and supplier demands.

4) Ensuring that the project delivers value for money.

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Question 19

Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?

Options:

A.

To use empiricism, based on knowledge that comes from experience

B.

To build, measure, learn from your experiences

C.

To create a minimum viable product to manage uncertainty

D.

To fail fast, if you are going to fail

Question 20

What is a purpose of the 'project closure' workshop?

Options:

A.

Align teams with project vision

B.

Create benefits management approach

C.

Update the project documentation

D.

Refine the release map for the next stage