Question 17
Which of the following is a prioritized list of the requirements for a product?
Options:
A.
Project canvas
B.
Release map
C.
Project log
D.
Backlog
Answer:
D
Explanation:
In PRINCE2 Agile, a Backlog is the prioritized list of requirements, features, or user stories that define what needs to be delivered for a product. It is a dynamic and evolving list that is continually refined and re-prioritized to ensure the most valuable work is done first. The backlog acts as a single source of truth for what the team needs to deliver and provides transparency to stakeholders regarding progress and priorities. It aligns with agile principles and practices such as Scrum, where the Product Backlog contains all desired work for the product.
The Project Canvas is a high-level tool used for defining project scope and objectives, the Release Map plans releases and iterations, and the Project Log tracks issues, risks, and actions but does not list prioritized requirements.
[Reference: PRINCE2 Agile Foundation Version 2, Section 5.3 "Agile Concepts," and PRINCE2 Agile Study Guide, Chapter 5, "Products and Backlogs.", , ]
Question 18
Which is an advantage of frequent releases?
Options:
A.
Releases can be used to replace management stages
B.
A ‘one-team’ culture in the project team is encouraged
C.
Configuration management becomes less important
D.
The delivery team becomes more experienced at product handover
Answer:
D
Question 19
Which describes the Scrum Master role in Scrum?
Options:
A.
It is authorized to run the project on a day-to-day basis on behalf of the project board
B.
It is responsible for ensuring that product backlog items are clearly expressed on the product backlog
C.
It is empowered to organize and manage its own work to create a valuable, useful increment every sprint
D.
It is servant-leadership to help everyone change their interactions to maximize the value created by the team
Answer:
B
Question 20
In which workshop does planning for the next stage occur?
Options:
A.
Team planning workshop
B.
Release planning workshop
C.
Team retrospective workshop
D.
Progress review workshop
Answer:
B
Explanation:
The Release Planning Workshop is the forum where planning for the next stage occurs in PRINCE2 Agile. This workshop brings together the project management team and delivery teams to plan the scope, schedule, and resources for the upcoming release or stage. It helps align business priorities with delivery capacity and supports incremental and iterative delivery approaches.
The Team Planning Workshop focuses on more detailed planning at the team level within the release, the Team Retrospective Workshop is dedicated to reflecting on performance and improving processes, and the Progress Review Workshop is for reviewing progress against the plan rather than planning future work.
[Reference: PRINCE2 Agile Foundation Version 2, Section 6.4 "Planning Workshops," and PRINCE2 Agile Study Guide, Chapter 7, "Planning.", , ]