Which statement is CORRECT with respect to the management of risk using PRINCE2 Agile?
Options:
A.
It should always be appropriate to the needs of the project
B.
It should always be addressed during the daily stand-ups
C.
It should always be carried out formally
D.
It should always be carried out informally
Answer:
A
Question 23
Which workshop reflects on lessons learned?
Options:
A.
Team planning workshop
B.
Agile enablement workshop
C.
Project kickoff workshop
D.
Project closure workshop
Answer:
D
Explanation:
The Project Closure Workshop is the formal forum used to reflect on lessons learned during the project lifecycle. It is held towards the end of the project and provides an opportunity for the project team, stakeholders, and sponsors to review successes, challenges, and areas for improvement.
Capturing lessons learned supports organizational learning, helps avoid repeating mistakes, and improves future projects and agile adoption. This reflective practice aligns with PRINCE2’s focus on continuous improvement and governance requirements.
Other workshops such as team planning (A) focus on upcoming work, agile enablement (B) on agile adoption, and project kickoff (C) on project initiation, none of which prioritize lessons learned reflection.
The project closure workshop is a vital practice to ensure knowledge retention and maturity in both traditional and agile project environments.
[Reference: PRINCE2 Agile Foundation Version 2, Section 9.2 "Closing a Project," and PRINCE2 Agile Study Guide, Chapter 9., , ]
Question 24
How is the ‘tailor to suit the project’ principle applied in an agile context?
Options:
A.
By flexing what is produced to stay in control and deliver value
B.
By emphasizing tolerances on what is being delivered
C.
By using the Agilometer to assess the project environment
D.
By fitting releases into planned management stages