Which statement about the ‘directing a project’ process is CORRECT?
The project board may pull reports from the information radiator
As a minimum, the project board should receive oral reports from the project manager
The project board should attend the delivery team’s daily stand up meeting
The project board should receive regular reports focusing on cost and time overruns
When tailoring PRINCE2, what does PRINCE2 Agile guidance cover?
How to adapt the PRINCE2 management products
How to select which Agile framework should be favoured
How to decide whether PRINCE2 is appropriate
How to calculate the project budget and cost tolerance
How should product-based planning be used as part of PRINCE2 Agile?
To track progress against the team plan
To create the project plan using empiricism
To enable team planning to be predictive
To plan by focusing on the features required
Which statement about velocity is CORRECT?
It is based on the concept of rationalism
It is shown by the ideal line on a bum-down chart
It describes how much work is getting done
It tracks the time and cost of a timebox