Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PeopleCert MSP-Practitioner Exam With Confidence Using Practice Dumps

Exam Code:
MSP-Practitioner
Exam Name:
MSP Practitioner, 5th edition Exam
Certification:
MSP
Vendor:
Questions:
133
Last Updated:
Feb 19, 2026
Exam Status:
Stable
PeopleCert MSP-Practitioner

MSP-Practitioner: MSP Exam 2025 Study Guide Pdf and Test Engine

Are you worried about passing the PeopleCert MSP-Practitioner (MSP Practitioner, 5th edition Exam) exam? Download the most recent PeopleCert MSP-Practitioner braindumps with answers that are 100% real. After downloading the PeopleCert MSP-Practitioner exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the PeopleCert MSP-Practitioner exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the PeopleCert MSP-Practitioner exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (MSP Practitioner, 5th edition Exam) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA MSP-Practitioner test is available at CertsTopics. Before purchasing it, you can also see the PeopleCert MSP-Practitioner practice exam demo.

MSP Practitioner, 5th edition Exam Questions and Answers

Question 1

Significant changes to the customer processes have been delivered and Tranche 2 is now complete. Many engineering staff do not believe that the Training Project is needed in Tranche 3 as they feel the changes to the new customer processes are minor. The programme manager is concerned that the engineering staff may have misunderstood the extent of the changes. As a result, the programme manager noted in the end-of-tranche report for Tranche 2, that there needs to be more engagement with engineering staff during subsequent tranches.

Is this recommendation an appropriate application of the 'evaluate new information' process, and why?

Options:

A.

Yes, because the end-of-tranche report should include a list of risks to the next tranche

B.

Yes, because the end-of-tranche report should report on the effectiveness of communications

C.

No, because the end-of-tranche report should focus on the programme’s financial performance

D.

No, because the end-of-tranche report should focus on progress towards the target operating model

Buy Now
Question 2

The programme manager has produced a rough estimate of costs based on the recently completed roll-out of smart metered services to electricity and gas customers.

Is this an appropriate application of the ‘identify the programme' process, and why?

Options:

A.

Yes, because time should not be wasted creating detailed costs and budgets during the identify the programme’ process

B.

Yes, because the programme manager needs to have some understanding of the cost before agreeing to proceed (or close)

C.

No, because a detailed financial plan will be developed to understand the costs during the ‘plan progressive delivery’ process

D.

No, because the previous roll-out of smart metering services was for electricity and gas, not water, and the costs will be different

Question 3

Which of following is correct about Benefits Management?

Options:

A.

Ensures programme does right things and is aligned with strategy

B.

Ensures programme is aware of positive and negative impact it might generate

C.

Is tightly aligned to transformational flow processes

D.

All of above