Oracle Planning and Collaboration Cloud 2023 Implementation Professional Questions and Answers

Question 1

The five pre-configured review stages of a Sales and Operations Planning process are Product Review, Demand Review, Supply Review, Financial Review, and Executive Review.

If Product Review is NOT an integral part of your company’s S&OP process, how do you configure the system to ignore it?

Options:

A.

In Manage Planning Cycles, right-click the Product Review tab. and select Delete.

B.

It is not possible to ignore any of the 5 pre-configured review stages.

C.

In Manage Planning Cycles, do not add any participants or tasks for the Product Review stage.

D.

In Manage Planning Cycles, go to the Actions menu, select Configure Stages, and set Enabled for Product Review to No.

Question 2

You want to check how many items have excess inventory. Which three choices will get you there? (Choose three.)

Options:

A.

Open Table, Graph, or Tile Set > Table: Item Exceptions Summary > Filter by Items with Excess Inventory

B.

Manage Plans > Edit Plan Options > Select Supply tab > Navigate to Item area > Filter by Items with Excess Inventory

C.

Open Table, Graph, or Tile Set > Table: Exceptions > Expand Supply Planning Exceptions > Select Items with Excess Inventory

D.

Open Table, Graph, or Tile Set > Table: Items with Exceptions > Filter by Items with Excess Inventory

E.

Open Table, Graph, Tile Set > Table: Items > Select any Item > Drill to: Item Exceptions > Expand Supply Planning Exceptions > Select Items with Excess Inventory > Refresh the search results

Question 3

As part of the agreement with one of your suppliers, you must always order product by the 100s. For example, if the required supply is 105, you must order 200, if it's 275, you must order 300. Which item attributes will help you achieve this?

Options:

A.

Minimum Order Quantity

B.

Fixed Lot Size Multiplier

C.

Maximum Order Quantity

D.

Fixed Order Quantity

E.

Rounding

Question 4

Identify two ways you can track performance against goals when defining measure goals. (Choose two.)

Options:

A.

Specification

B.

Value

C.

Range

D.

Aggregation

E.

Quantity

F.

Attribute

Question 5

In order for Supply and Demand Plans to run successfully, which three Configure Planning Analytic tasks must be completed? (Choose three.)

Options:

A.

Set up Levels and Attributes

B.

Set up Measure Catalogs

C.

Run the Configure Dimension Catalog process

D.

Set up Default Catalogs

E.

Set up Dimension Catalogs

F.

Set up Hierarchy Attributes

Question 6

What are two characteristics of an ‘Item’ organization? (Choose two.)

Options:

A.

It includes parameter definition, including lot. serial number, and item sourcing rules.

B.

It requires financial and accounting setups.

C.

It does not physically of financially track material storage or movement.

D.

It is ideal for deployments where inventory management may not be installed.

Question 7

You are in Implementation project and your customer is a global company with a complex supply chain network. Planners work across different geographies and different line of products. Each planner works with their own set of data and analysis and dashboards.

How do you configure the application so each planner can have their own custom dashboard view-able only to themselves?

Options:

A.

Create public page layouts that are tailored to specific business needs.

B.

You cannot create custom dashboards by user.

C.

Enable layout security checkbox in the Administer Planning Security.

D.

Create private page layouts that are tailored to specific business needs.

Question 8

Which three statements are true regarding exceptions? (Choose three.)

Options:

A.

The conditions under which exceptions are generated can be modified.

B.

You can act on an exception by selecting it and clicking 'Resolve exception'. A list of ways to resolve will be generated.

C.

The calculation logic for exceptions can be modified.

D.

You can drill down into Supplies and Demand from an exception line.

E.

You can export exception tables to Excel.

F.

You can create custom exceptions.

Question 9

Your client has operations in the west coast of the US. If the customer is in the western half of the US, then they would like to ship the product from their warehouses. If it's in the eastern half of the US, then they want to drop ship it from a supplier.

How would you recommend they set the assignment up?

Options:

A.

Set up a region for the west coast warehouse and an item-region level assignment for the drop ship.

B.

Set up two region level assignments, one for the west coast and the other for the east coast.

C.

Set up by each customer for the customers who should get product from each warehouse.

D.

Set up an item-region assignment for the west coast warehouse and a region level assignment for the drop ship.

E.

Set up an item-organization assignment for the west coast warehouse and an item-organization level assignment for the drop ship.

Question 10

Which statement is correct regarding S&OP plan options?

Options:

A.

Calculating Safety Stock can optionally be included.

B.

Forecasting profile's input demand measure can only be set to 'consensus forecast' or 'approved consensus forecast'.

C.

Supply Planning Mode 'aggregated' can be turned off.

D.

Lead time compression can optionally be included as a legitimate plan constraint.

Question 11

Your customer wants to display a numeric measure in both pound and kilogram Units of Measure (UOM) on a table. Describe the configuration steps to display a measure in two UOMs.

Options:

A.

Open a table and select Actions, View Table Configuration and click UOM tab. Select primary UOM as pound and secondary UOM as kilogram.

B.

Open a table and select View, Format Measures to find the measure. Now select pound as primary UOM and kilogram as secondary UOM.

C.

Open a table and select Actions, View Table Configuration and click Measure tab. Find the measure, duplicate the measure, and rename it. Now select pound as UOM for the original measure and kilogram as UOM for the duplicated measure.

D.

Open a table and select View, Format Measures to find the measure. Duplicate the measure and rename it. Now select pound as UOM for the original measure and kilogram as UOM for the duplicated measure.

Question 12

Which two statements are true regarding Planning Business Flows? (Choose two.)

Options:

A.

Inventory Planning cannot run in the Planning Business Flows.

B.

You can analyze and adjust data at any stage of the process.

C.

In automated plans, all release rules must be automatic.

D.

Demand and Supply Planning have to be run in separate business flows.

E.

Planners can set up automatic release rules or release orders manually as part of the plan execution.

Question 13

As part of the agreement with one of our suppliers, you are supposed to order product by the 100s. But if the required supply is only 149, how many should be planned to purchase, and which item attribute will cause this to happen?

Options:

A.

Planned Order for 200. Maximum Order Quantity enabled

B.

Planned Order for 100. with Minimum Order Quantity enabled

C.

Planned Order for 150, with Rounding enabled

D.

Planned Order for 200. with Fixed Lot Size Multiplier enabled

E.

Planned Order for 149, with Fixed Order Quantity enabled

Question 14

When duplicating a supply plan, which parameters can you modify if Copy Type is “copy plan options only”?

Options:

A.

Name, Access. Owner, and Notes

B.

Name, Description. Access (but if the original plan was private, you can't edit the Users list), and Notes

C.

Name, Description. Access. Supply Planning Mode, and Owner

D.

Name, Description. Access. Owner. Include Archive, and Notes

Question 15

Your Procurement Department is getting ready to set up Approved Supplier Lists that will be needed for Supply Planning. They ask you for what you need on the ASLs for planning usage. Which three options are key for planning? (Choose three.)

Options:

A.

Make sure to include Maximum Order Quantities.

B.

Make sure to include Minimum Order Quantities.

C.

Make sure to include Fixed Lot Multipliers.

D.

Make sure to include Fixed Order Quantities.

E.

Make sure they are at a Global level.

F.

Make sure all Local level ASLs include an Organization.

Question 16

Your client has reviewed all of the current graphs available for the plans, but cannot find one that shows them exactly what they want for the Days of Supply. How can this key performance indicator be added?

Options:

A.

Go to Configure Planning Analytics > Actions > Manage Tables, Graphs, and Analysis Sets, and edit the current 'Days of Supply' graph to meet the client needs.

B.

Go to Configure Planning Analytics > Actions > Manage Tables, Graphs, and Analysis Sets, and add a new graph with the requested data.

C.

Open the plan and go to Actions > Manage Tables, Graphs, and Analysis Sets, and edit the current 'Days of Supply' graph to meet the client needs.

D.

It is not possible to add new or change the current graphs.

E.

Open the plan and go to Actions > Manage Tables, Graphs, and Analysis Sets, and add a new graph with the requested data.

Question 17

The marketing department of a company needs to analyze the forecast based on type of demand (large retailer versus specialty store) and item cost (low versus high).

After creating a segment group with demand class and product for segment granularity, what additional sequence of actions must they also perform to satisfy marketing?

Options:

A.

Define four segments based on demand type and item cost, define each segment's criteria, execute segmentation, and use the selector tool to create a new table or graph.

B.

Define four segmentation based on demand type and item cost, define each segment's criteria, execute segmentation, configure planning analytics to update the dimension catalog, and use the selector tool to create a new table or graph.

C.

Define four segments based on demand type and item cost, execute segmentation, and use the selector tool to create a new table or graph.

D.

Define two segments based on demand type and item cost, execute segmentation, and use the selector tool to create a new table or graph.

Question 18

You are viewing a drop shipment plan for your organization and you want to know which customer the purchase order will be shipped to. Where can you see that?

Options:

A.

You need to first drill down to the sales order from the supply-demand link, then open the sales order to get the customer.

B.

It is visible in the drop ship analytics.

C.

It is not viewable at this time.

D.

You can see the customer on the supply in Supplies and Demand.

E.

You can see the supplier on the sales order, but not vice-versa.

Question 19

During the FIFO pegging process, what is the correct order in which the supplies are sorted?

Options:

A.

Peg demands with reservations first and then peg demands that do not have reservations

B.

Pegging process sorts demands by due dates followed by reservation status

C.

Peg unreserved demands first and then demands with reservations

D.

Pegging process does not respect reservation, and demands are sorted based on demand and supply types

E.

Pegging process does not respect reservation, and demands are sorted based on due dates

Question 20

Which two statements regarding the Decomposition scheduled process are incorrect? (Choose two.)

Options:

A.

It does not recognize forecast exceptions.

B.

It reads published planning data from interface tables.

C.

It received supplier commits.

D.

It creates or updates an order forecast, used by Supply Chain Collaboration to publish to suppliers.

Question 21

What happens when a demand planner approves a demand plan and then adjusts shipment history and runs demand plan again?

Options:

A.

The approve action takes the data from the two final forecast measures and copies to Approved Final Shipments Forecast and Approved Final Bookings Forecast, respectively. After a forecast is approved, the approved values remain unchanged until the forecast is approved again.

B.

The approve action makes the Adjusted Shipments Forecast and Adjusted Bookings Forecast measures "not editable." After a forecast is approved, the Final Shipments Forecast and Final Bookings Forecast measures remain unchanged until the forecast is approved again.

C.

The approve action makes the Adjusted Shipments Forecast and Adjusted Bookings Forecast measures "not editable." But any subsequent demand plan run can change Final Shipments Forecast and Final Bookings Forecast values.

D.

The approve action takes the data from the two final forecast measures and copies to Approved Final Shipments Forecast and Approved Final Bookings Forecast, respectively. Any subsequent demand plan run can change final shipments or bookings forecast values that will automatically update the approved forecast measures.

Question 22

You want to understand what your inventory turns are for your organization. Where can you see this information in Planning Central?

Options:

A.

Manage Planning Analytics

B.

Manage Planning Measures

C.

View Planning Analytics

D.

Manage Metrics

E.

Plan Summary

Question 23

Which list of parameters is available for selection when you run the Start Backlog Planning scheduled process?

Options:

A.

Priority Rule. Organization. Demand Class, Item. Customer

B.

Demand Priority Rule. Organization. Demand Class. Item. Customer

C.

Backlog Priority Rule. Organization. Category. Item. Customer

D.

Demand Priority Rule. Organization. Category. Item, Customer

Question 24

You ran a demand plan and you are reviewing the shipments forecast value measure. It is always zero for a particular item. Identify the root cause of this problem.

Options:

A.

In planning measures catalog, shipment forecast value measure is not enabled at item and organization level.

B.

In plan parameters, Item List Price marked as primary does not have price defined for the particular item.

C.

In plan parameters, shipment forecast value measure expression is not defined.

D.

In planning measures catalog, shipment forecast measure is not enabled at item and organization level.

Question 25

During an implementation, customer is in the process of planning supply requirements. Customer also needs to generate forecast and safety stock levels. Which plan type on the plan options should the customer be running?

Options:

A.

Demand and Supply Plan

B.

Safety Stock and Forecast Plan

C.

Demand Plan

D.

Supply Plan

E.

Integrated Plan

Question 26

Your customer has seasonal demand and wants to generate forecast for next six months. You ran a demand plan for first time using six months of shipments history but the forecast accuracy was low.

Identify two statements that are true in this scenario. (Choose two.)

Options:

A.

Running a demand plan with both shipments and booking forecast profile is required to forecast seasonal demand.

B.

Running a demand plan with less than one year of history will impact seasonal analysis.

C.

Running a demand plan with both shipments and seasonal shipments forecast profile is required to forecast seasonal demand.

D.

Running a demand plan with six months of booking history instead of six months of shipment history is required for seasonal demand.

E.

Running a demand plan with 18 to 36 months of shipments history is recommended.

Question 27

You are defining material planners for your organization. However, when you go to Manage Material Planners, your organization does not appear in the list of values. Why?

Options:

A.

The organization was not enabled for collection under Manage Planning Source Systems.

B.

The organization must be enabled in Manage Planning Parameters.

C.

The organization is an Item Organization.

D.

The organization must be enabled in Manage Planning Profile Options.

E.

You do not have data access to the organization.

Question 28

During Implementation of Planning Central, your client has discovered that no Material Planners have been defined in Manage Material Planners in Planning Central.

In this situation, which three statements are true? (Choose three.)

Options:

A.

Your client has not been assigned the Material Planner role.

B.

You have not been assigned the Materials Planner role.

C.

The Planner field will be null for all items.

D.

Collect Planning Data has not been run for Material Planners.

E.

Planned Orders will not release successfully.

Question 29

How can you deliver a forecast for drop shipments?

Options:

A.

It cannot be done at this time.

B.

Generate manually using Planning Analytics

C.

Excel upload using File Based Data Import Process

D.

Create based on the supplier performance for drop shipment collection

E.

Create based on the drop shipment or booking history; the ship from will be the drop ship validation organization

Question 30

Which calendar is supported in the supply planning process but does not support bucketing by week?

Options:

A.

Lunisolar

B.

Fiscal

C.

Roman

D.

Gregorian

E.

Julian