Weekend Sale Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Supply Chain Planning Cloud Changed 1z0-1066-23 Questions

Page: 6 / 8
Total 109 questions

Oracle Planning and Collaboration Cloud 2023 Implementation Professional Questions and Answers

Question 21

What happens when a demand planner approves a demand plan and then adjusts shipment history and runs demand plan again?

Options:

A.

The approve action takes the data from the two final forecast measures and copies to Approved Final Shipments Forecast and Approved Final Bookings Forecast, respectively. After a forecast is approved, the approved values remain unchanged until the forecast is approved again.

B.

The approve action makes the Adjusted Shipments Forecast and Adjusted Bookings Forecast measures "not editable." After a forecast is approved, the Final Shipments Forecast and Final Bookings Forecast measures remain unchanged until the forecast is approved again.

C.

The approve action makes the Adjusted Shipments Forecast and Adjusted Bookings Forecast measures "not editable." But any subsequent demand plan run can change Final Shipments Forecast and Final Bookings Forecast values.

D.

The approve action takes the data from the two final forecast measures and copies to Approved Final Shipments Forecast and Approved Final Bookings Forecast, respectively. Any subsequent demand plan run can change final shipments or bookings forecast values that will automatically update the approved forecast measures.

Question 22

You want to understand what your inventory turns are for your organization. Where can you see this information in Planning Central?

Options:

A.

Manage Planning Analytics

B.

Manage Planning Measures

C.

View Planning Analytics

D.

Manage Metrics

E.

Plan Summary

Question 23

Which list of parameters is available for selection when you run the Start Backlog Planning scheduled process?

Options:

A.

Priority Rule. Organization. Demand Class, Item. Customer

B.

Demand Priority Rule. Organization. Demand Class. Item. Customer

C.

Backlog Priority Rule. Organization. Category. Item. Customer

D.

Demand Priority Rule. Organization. Category. Item, Customer

Question 24

You ran a demand plan and you are reviewing the shipments forecast value measure. It is always zero for a particular item. Identify the root cause of this problem.

Options:

A.

In planning measures catalog, shipment forecast value measure is not enabled at item and organization level.

B.

In plan parameters, Item List Price marked as primary does not have price defined for the particular item.

C.

In plan parameters, shipment forecast value measure expression is not defined.

D.

In planning measures catalog, shipment forecast measure is not enabled at item and organization level.

Page: 6 / 8
Total 109 questions