Planning & Scheduling Professional (PSP) Exam
Certification:
Questions:
163
Last Updated:
Apr 30, 2025
Exam Status:
Stable
AACE International PSP

PSP: Professional Level Exam 2025 Study Guide Pdf and Test Engine

Are you worried about passing the AACE International PSP (Planning & Scheduling Professional (PSP) Exam) exam? Download the most recent AACE International PSP braindumps with answers that are 100% real. After downloading the AACE International PSP exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the AACE International PSP exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the AACE International PSP exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (Planning & Scheduling Professional (PSP) Exam) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA PSP test is available at CertsTopics. Before purchasing it, you can also see the AACE International PSP practice exam demo.

Related AACE International Exams

Planning & Scheduling Professional (PSP) Exam Questions and Answers

Question 1

If a new hammock activity covering activities 6001 through 6003 is developed, what are governing predecessor and successor activities?

Options:

A.

Predecessor is Activity 4001. successor is Activity 9004

B.

Predecessor is Activity 8001, successor is Activity 5001

C.

Predecessor is Activity 5001, successor is Activity 8001

D.

Predecessor is Activity 4001, successor is Activity 9003

Buy Now
Question 2

When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?

Options:

A.

Projected crew size

B.

Estimated labor hours

C.

Hours in a standard work day

D.

Estimated cost

Question 3

Assuming activities 2001 through 2004 comprise the same WBS element, construct a WBS summary activity for activities 2001 through 2004. Use the normal schedule, what is the cost of the activity?

Options:

A.

$289.000

B.

$321.000

C.

$193,000

D.

$327,000