New Year Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

AACE International CCP Exam With Confidence Using Practice Dumps

Exam Code:
CCP
Exam Name:
Certified Cost Professional (CCP) Exam
Certification:
Questions:
189
Last Updated:
Dec 23, 2025
Exam Status:
Stable
AACE International CCP

CCP: AACE Certification Exam 2025 Study Guide Pdf and Test Engine

Are you worried about passing the AACE International CCP (Certified Cost Professional (CCP) Exam) exam? Download the most recent AACE International CCP braindumps with answers that are 100% real. After downloading the AACE International CCP exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the AACE International CCP exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the AACE International CCP exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (Certified Cost Professional (CCP) Exam) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA CCP test is available at CertsTopics. Before purchasing it, you can also see the AACE International CCP practice exam demo.

Related AACE International Exams

Certified Cost Professional (CCP) Exam Questions and Answers

Question 1

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Depreciation (in the United States) is calculated in accordance with which of the following?

Options:

A.

Modified Accelerated Cost Recovery System (MACRS)

B.

The Federal IRS Reform Act (FIRSRA)

C.

Generally Accepted Accounting Practices (GAAP)

D.

Accelerated Cost Recovery System (ACRS)

Buy Now
Question 2

SCENARIO: A can manufacturing company requested you to provide data for their decision making The unit prices of the can varies but an average selling price of $0.55 cents and average cost of SO 45 cents is estimated.

The monthly fixed costs are: Rant-$1,600

Wages - S4.000

Miscellaneous fixed expenses - $500

If the rent increases by 100% and the unit sales/other costs remain unchanged, the new break even amount is?

Options:

A.

$33,750

B.

$375,00

C.

$7,500

Question 3

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

When analyzing a precedence diagram schedule, the "backward pass"

Options:

A.

Allows total float to be calculated

B.

Determines the duration of each activity

C.

Calculates the earliest allowable start and finish times for the activities in the schedule

D.

Allows activities to finish as soon as all their 'predecessor' relationships are satisfied