Question 1

Inputs to prepare for elicitation include:

Options:

A.

information management approach and solution scope.

B.

needs and stakeholder engagement approach.

C.

future state description and risk analysis results.

D.

requirements and designs.

Question 2

When stakeholder collaboration is not properly managed, poor relationships can have the following damaging effect on business analysis:

Options:

A.

strong negative reactions to obstacles.

B.

lack of support for organizational goals.

C.

resistance to approving elicitation results.

D.

failure to meet project deadlines.

Question 3

The process of assigning requirements to solution components and releases to best achieve the objectives is called:

Options:

A.

requirements classification schema.

B.

requirements traceability.

C.

requirements allocation.

D.

requirements architecture.

Question 4

Which of the following is an activity that a business analyst (BA) performs to prepare for elicitation?

Options:

A.

Assess risk

B.

Trace requirements

C.

Secure supporting material

D.

Analyze performance measures

Question 5

If inconsistencies arise between different elicitation results, the business analyst (BA) should:

Options:

A.

escalate them to the business sponsor.

B.

report them to the project manager.

C.

resolve them through collaboration.

D.

reconcile them through experience.

Question 6

Requirements allocation is an element of which task?

Options:

A.

Specify and model requirements

B.

Verify requirements

C.

Define requirements architecture

D.

Define design options

Question 7

Which type of requirements are temporary in nature?

Options:

A.

Business requirements

B.

Solution requirements

C.

Stakeholder requirements

D.

Transition requirements

Question 8

Which business analysis activity ensures that a set of requirements or designs delivers business value and supports the organization’s goal and objectives?

Options:

A.

Define solution options

B.

Verify requirements

C.

Validate requirements

D.

Define requirements architecture

Question 9

Which of the following tasks is included in the requirements analysis and design definition knowledge area?

Options:

A.

Assess requirements changes

B.

Recommend actions to increase solution value

C.

Analyze potential value and recommend solution

D.

Define change strategy

Question 10

The requirements elicitation technique used to iteratively validate the needs of stakeholders that interact with the application is:

Options:

A.

interface analysis

B.

observation.

C.

prototyping

D.

reverse engineering.

Question 11

Why should a business analyst (BA) perform a cultural assessment when analyzing the current state of an enterprise?

Options:

A.

To determine whether stakeholders understand the rationale for the current state of the enterprise

B.

To identify the formal relationships between people working in the enterprise

C.

To document the communication channels, reporting structures, and relationships in the enterprise

D.

To understand the scope of decision making at different levels of the enterprise

Question 12

What is a valid reason for prioritization?

Options:

A.

Requirements which are of significant personal interest to a stakeholder

B.

Effort and resources needed to implement a requirement

C.

Sponsor’s wish-list

D.

Development team’s advice to implement easy requirements

Question 13

Which of the following approaches is used to determine how business analysis data will be packaged and communicated to stakeholders?

Options:

A.

Business Analysis Approach

B.

Information Management Approach

C.

Governance Approach

D.

Stakeholder Engagement Approach

Question 14

What type of requirements describes the needs of those participating in or impacted by business analysis activities?

Options:

A.

Solution

B.

Business

C.

Stakeholder

D.

Technical

Question 15

What is the main purpose of the “Approve Requirements” task?

Options:

A.

Obtain agreement

B.

Establish requirements baseline

C.

Select appropriate techniques

D.

Assess alternative approaches

Question 16

A business analyst (BA) is someone who elicits the actual needs of organizational stakeholders:

Options:

A.

in any capacity, regardless of job title.

B.

in a project team, with an “analyst” job title.

C.

in a project team, regardless of job title.

D.

in any capacity, with an “analyst” job title.

Question 17

The task that uses the elicitation activity plan to draw out, explore and identify information relevant to the change is:

Options:

A.

conduct elicitation.

B.

prepare for elicitation.

C.

plan business analysis information.

D.

confirm elicitation results.

Question 18

Conducting elicitation by asking Questions and documenting responses from relevant stakeholders has the following strength:

Options:

A.

prioritization setting.

B.

analytical thinking.

C.

sharing of information.

D.

encouraging participation.

Question 19

When initially assigned work, understanding the scope of elicitation is important in order to:

Options:

A.

review the project charter.

B.

identify the stakeholders.

C.

discover the requirements.

D.

plan the business analysis approach

Question 20

In a use case, which is one of the two commonly used relationships?

Options:

A.

Inherit

B.

Identify

C.

Distribute

D.

Extend

Question 21

Which of the following are criteria used to determine quality requirements relationships?

Options:

A.

Necessity, validate, derive

B.

Complexity, stability, status

C.

Necessary, consistent, correct

D.

Penalty, benefit, cost

Question 22

What is a definitional rule?

Options:

A.

A representation of the operational knowledge of the organization

B.

An obligation or prohibition of conduct, action, practice, or procedure

C.

A rule that can be violated

D.

A representation of the behavior of people

Question 23

Which of the following activities are performed during the requirements life cycle management phase?

Options:

A.

Elicit Requirements

B.

Prioritize Designs

C.

Trace Requirements

D.

Maintain Attributes

Question 24

Which core concept defines a specific way of satisfying one or more needs in a context?

Options:

A.

Value

B.

Change

C.

Solution

D.

Priority

Question 25

Which behavioural characteristic enables the business analyst (BA) to establish credibility by ensuring that business analysis efforts meet the needs of the business?

Options:

A.

Ethics

B.

Trustworthiness

C.

Personal Accountability

D.

Adaptability

Question 26

Who is responsible for discovering, synthesizing, and analyzing information within an enterprise?

Options:

A.

Project manager

B.

Business analyst

C.

Programmer

D.

Project sponsor

Question 27

Which approach aligns to approval of requirements at the end of a phase?

Options:

A.

Adaptive

B.

Modelling

C.

Predictive

D.

Prioritization

Question 28

Which of the following business analysis activities might be undertaken to verify requirements?

Options:

A.

Identifying a previously documented business need

B.

Comparing a model with another relevant model

C.

Organizing requirements into structures

D.

Evaluating alignment with solution scope

Question 29

What tool can be used to determine the impact of a changed requirement on other requirements?

Options:

A.

Verification

B.

Traceability

C.

Interview

D.

Workshop

Question 30

Which of the following is an input to the prepare for elicitation task?

Options:

A.

Elicitation activity plan

B.

Set up logistics

C.

Potential value

D.

Needs