Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Scrum SPS Exam With Confidence Using Practice Dumps

Exam Code:
SPS
Exam Name:
Scaled Professional Scrum (SPS) Exam
Certification:
Vendor:
Questions:
40
Last Updated:
Dec 13, 2025
Exam Status:
Stable
Scrum SPS

SPS: Scaled Professional Scrum Exam 2025 Study Guide Pdf and Test Engine

Are you worried about passing the Scrum SPS (Scaled Professional Scrum (SPS) Exam) exam? Download the most recent Scrum SPS braindumps with answers that are 100% real. After downloading the Scrum SPS exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the Scrum SPS exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the Scrum SPS exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (Scaled Professional Scrum (SPS) Exam) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA SPS test is available at CertsTopics. Before purchasing it, you can also see the Scrum SPS practice exam demo.

Scaled Professional Scrum (SPS) Exam Questions and Answers

Question 1

Scenario C: Dependencies and Product Backlog items

During Nexus Sprint Planning, representatives from each of the 9-member Scrum Teams

identify many dependencies. This makes it hard for them to choose the work they could pull

into their individual teams for the next Sprint. No matter how they reorganize the Product

Backlog items, they continually find more or new dependencies.

What should the Scrum Teams do to effectively deal with their dependencies?

(choose the best answer)

Options:

A.

Increase the frequency of Cross-Team Refinement to reduce dependencies.

B.

Merge the two Scrum Teams together that have the most dependencies with each

other.

C.

Institute quarterly meetings for planning out all dependencies between teams.

D.

All of the above.

Buy Now
Question 2

Four teams in a Nexus typically integrate their work only once, late in the Sprint. The teams

report that it takes many hours or days to integrate their work, which delays the Sprint's end. To

address this issue, which of the following would help?

(choose the best answer)

Options:

A.

Integrating more frequently.

B.

Doing more acceptance testing.

C.

Doing more exploratory testing.

D.

Using Behavior-Driven Development.

E.

Investing in more Requirements Traceability.

F.

All of the above.

Question 3

The purpose of the Nexus Integration Team is to:

(choose the best two answers)

Options:

A.

Raise transparency.

B.

Manage the Nexus.

C.

Be accountable that an Integrated Increment is produced.

D.

Integrate the work of the Scrum Teams.