Vce C_ACTIVATE22 Questions Latest

SAP Certified Associate - SAP Activate Project Manager Questions and Answers

Question 17

Which of the following is a key characteristic of the Agile project approach?

Options:

A.

Frequent quality gates

B.

Frequent and detailed project scheduling

C.

Formal and detailed documentation

D.

Iterative build with frequent inspections

Question 18

Which of the following are capabilities of the test automation tool for SAP S/4HANA Cloud, public edition?Note: There are 2 correct answers to this question.

Options:

A.

Raises test defects automatically

B.

Supports recording of transaction-based processes

C.

Captures test results with screenshots

D.

Supports the creation of custom test automates

Question 19

Which of the following is part of the Explore phase in the "New Implementation of SAP S/4HANA Cloud, public edition" transition path?

Options:

A.

Solution Validation and Delta Design

B.

Fit-to-standard

C.

Simplification and Custom Code Impact Analysis

D.

Setup and Enablement

Question 20

When performing an SAP Readiness Check in system conversion, what areas are covered within the result?Note: There are 3 correct answers to this question

Options:

A.

Recommended SAP Fiori apps

B.

SAP and third party interfaces

C.

Sizing for SAP S/4HANA

D.

Active business functions

E.

Simplification database