Which of the following statements about test management activities for an iterative development model is false?
You are a test manager in charge of integration, system, and acceptance testing for a bank. You are working on a project to upgrade an existing ATM to allow customers to obtain cash advances from supported credit cards. The system should allow cash advances from €20 to €500 (both inclusive) for all supported credit cards. The supported credit cards are American Express, VISA, Eurocard, and Mastercard. The system should be easy to use for all users, including new users.
In the master test plan, the following items are listed in the section named "items and/or features to be tested":
I. All supported credit cards
II. Language localisation
III. Valid and invalid advances
IV. Usability
Assume that the project has now been completed, and the ATM system has been in use for just over two months. You are planning a retrospective meeting for the testing work performed.
Which of the following areas is most likely to be considered in this retrospective?
When reading books and watching recorded videos are used as a way to acquire skills and knowledge, which approach to competence development is typically being used?
You are a tester working in an Agile team in the finance domain. The team consists of 6 members, and you are the only tester. The team is responsible for the development and maintenance of a mobile front-end application. The application is considered to be critical with respect to customer impact and market branding.
You have been asked to identify which test management activity needs to be performed within the team to enhance test maturity and achieve a higher level of product quality.
Which test management activity would you recommend the team should adopt?