ISTQB Certified Tester Advanced Level - Test Management v3.0 Questions and Answers

Question 9

Test control uses the information from test monitoring to provide guidance and take corrective action when required.

Which of the following is not a possible test control action?

Options:

A.

Re-prioritisation of test cases

B.

Adjusting the test schedule

C.

Checking the fulfilment of the exit criteria

D.

Adding new resources

Question 10

Which of the following tools help to understand which part of the test object has been exercised by testing?

Options:

A.

Requirements management tool

B.

Test execution tool

C.

Static analysis tool

D.

Code coverage tool

Question 11

You are a test manager developing a master test plan. As part of the master test plan, you are defining exit criteria for the various test levels.

Which of the following exit criteria would be most appropriate and SMART for component testing, and which one would be most appropriate and SMART for system testing?

i. 95% of the tests prepared are executed successfully

ii. All test cases have been run

iii. 80% decision coverage for all tests run

iv. At least 30 defects have been found

v. At least two weeks of test execution

vi. No more open defects

Options:

A.

iii for component testing, v for system testing

B.

ii for component testing, iv for system testing

C.

iii for component testing, i for system testing

D.

v for component testing, vi for system testing

Question 12

You are working as a test manager at a company that develops software applications for the mobile domain. The organisation has recently been assessed against TMMi. This assessment showed that the company is a TMMi level 1 organisation. The projects use the V-model lifecycle and an independent test team exists. The test team consists of both experienced and novice testers. The team has not yet been formally trained in testing, but an ISTQB Foundation course is scheduled to take place in two months.

In your role as a test manager working in the independent test team, you have recently performed a risk assessment for a mobile software application to be developed. You want the features that have been identified as major risks to be tested more thoroughly.

Which test practice would you propose to mitigate the identified major product risks?

Options:

A.

Assign the most experienced testers to test the features with the highest risk levels

B.

Use test design techniques such as equivalence partitioning and decision table testing

C.

Start a test improvement project to achieve TMMi level 2

D.

Create pairs of developers and testers to test the features with the highest risk levels together