Weekend Sale Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Test Manager Advanced CTAL-TM ISTQB Study Notes

Page: 4 / 5
Total 65 questions

Certified Tester Advanced Level Test Manager (CTAL-TM) Questions and Answers

Question 13

You are reviewing the project's traceability matrix after the first cycle of testing. You have discovered that new requirements have been introduced and others have

changed.

What should you do? [2]

Options:

A.

Assign the new requirements to a maintenance release, update the test documentation for the changed requirements.

B.

Ask for more time and budget for testing.

C.

Update the "lessons learned" document to avoid future issues similar to this.

D.

Re-assess the test coverage.

Question 14

When closing out a defect report, which of the following developer commentaries is most likely to motivate a tester? [1]

Options:

A.

Rejected - system is functioning as designed

B.

Fixed - minor usability issue, wasn't worth the time to fix it

C.

Fixed - error in build caused compatibility issues

D.

Rejected - would take too long to fix

Question 15

What is the primary use for the traceability information regarding the relationship between test results and test conditions during test execution? [2]

Options:

A.

The Test Manager uses this information to control the test execution effort.

B.

The development manager uses this information to determine how many developer resources to allocate to defect repair.

C.

The project manager uses this information to determine if the project is on schedule.

D.

The tester uses this information to determine which test should be run next.

Question 16

Mary is an external IT auditor. She is conducting a review of the system-level testing done by Greg's functional testing team.

Which of the following items from Mary's assessment summary should concern Greg the most? [2]

Options:

A.

All the Business requirements could be traced to Test Objectives. However there was no tracing from the Business Requirements to the project's test

schedule.

B.

Some of the Test Objectives could only be mapped back to a single Business Requirement.

C.

A few of the Test Objectives did not have any Test Conditions assigned to them.

D.

There were Test Conditions which didn't tie back to any Business Requirement.

Page: 4 / 5
Total 65 questions