Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

CTAL-TM Reviews Questions

Page: 3 / 17
Total 228 questions

Certified Tester Advanced Level Test Management (CTAL-TM) v3.0 Questions and Answers

Question 9

You are the Test Manager of a four-person test team working for a small distribution company with a single warehouse. Your team has been working with a third party development team on a new

inventory management system. The company expects this system to generate approximately one million dollars per annum in profits for the company. Early in the project, various risks were

identified, and steps taken to mitigate those risks.

For example, you sent your test team for training on the new system, and upgraded the test environment. There are still some lingering risks that have not been addressed, but they have been

determined to have a low chance of occurring, with minimal impact if they do occur.

What would be the best option to mitigate these remaining risks? [3]

Options:

A.

Note the risks, and ignore them for now.

B.

Redo the project test plan to add additional testing for these risk items.

C.

Contract with the Risk Protection Insurance company to assume these risks at a cost of $500,000 per annum.

D.

Create a cross-functional team to work to reduce the impact and likelihood of these risks coming to fruition.

Question 10

You are the Test Manager on a new project. The schedule is aggressive and will require the team to work at peak efficiency. The requirements are not well defined yet, but it is clear that the

project will be using new technologies. To help the developers meet the development schedule, an offshore group will be added to the development team.

At this time there is not enough budget to add more testing resources. The project stakeholders are very concerned about the quality of delivered product and will be watching the project closely,

particularly during the testing cycles. The exit criteria from the system test level require no open high priority/severity defects, 100% pass rate for all test cases covering risks that are classified as

"high" or "very high", 90% pass rate for all "medium" risks and 50% pass rate for all "low" and "very low" risks.

Given this information, which lifecycle model should you recommend? [3]

Options:

A.

Spiral

B.

Iterative/incremental

C.

V-model

D.

Waterfall

Question 11

Which one of the following is NOT a determining factor when considering the optimal time to conduct a document review? SELECT ONE OPTION

Options:

A.

Management procedures have been reviewed

B.

Review time is built into the schedule.

C.

The document is in a reviewable state.

D.

Suitably skilled reviewers are available.

Question 12

You are a Test Manager and have started a program of test process improvement. You are following the IDEAL model and have completed the first three phases, now you are ready to go further. Which TWO of the following activities will enable you to complete the remaining phases of the IDEAL model?

Options:

A.

Trial a low-priority improvement in order to assess the difficulty of changing the organisation's processes

B.

Re-prioritise the possible improvements according to their expected return on Investment

C.

Trial one or more of the highest-priority improvements in a pilot project

D.

Decide whether to take a model based or an analytical based process improvement approach

E.

Check to see which benefits have, or have not, been achieved from the improvement made

Page: 3 / 17
Total 228 questions