You have assembled the following cost of quality numbers 1 000 defects were found prior to release and 100 were found after.
Given this information what should you conclude?
You are working on a project where the business part of the organization works traditionally with defined requirements, but the development team follows an Agile model Neither team plans to change their approach What is the proper name for this type of project approach''
Which of the following best describes the appraisal costs in the cost of quality'
At what testing level do the test management activities Include coordinating with end users7