Program Management Professional (PgMP) Questions and Answers

Question 65

Mike is the program manager of the NHQ Program. Mike and a vendor are in disagreement over the deliverable the vendor has created for Mike's program. Mike does not believe the vendor has correctly created the deliverable, while the vendor is adamant that his company has indeed completed the contract. Both parties have documented their stance in the debate.

This is an example of what?

Options:

A.

Breach of contract

B.

Issue

C.

Risk

D.

Claim

Question 66

A program to implement a new payroll processing system at a healthcare company is nearing completion and is under budget.

What should the program manager do next?

Options:

A.

Request permission from the program governance board to initiate program closure activities.

B.

Present additional opportunities to the program sponsor.

C.

Apply the remaining budget to operational activities.

D.

Apply the remaining budget to deferred enhancement requests.

Question 67

Performing quality assurance in a program can result in which one of the following?

Options:

A.

Quality control execution

B.

Scope fulfillment

C.

Quality management plan

D.

Change requests