Question 37

Which of the following can be used to help you or other project managers on future projects?

Options:

A.

Sponsor

B.

Charter

C.

Stakeholder

D.

Documentation

Question 38

A company is building a global monitoring network in 40 countries. The program completes the planning phase and a review is conducted of the program components’ strategic alignment with the intended program and company goals. The review identifies issues that should be resolved to improve program progress. One of the issues identified is the lack of incorporation of both software and configuration management tools.

Which of the following must be addressed?

Options:

A.

Program performance monitoring and controlling

B.

Program management information system (PMIS)

C.

Program delivery management

D.

Program roadmap

Question 39

You are a program manager for a large construction program. You need to ensure that the projects in the program are in accordance with the schedule. You are tracking start and finish dates for them. Which of the following processes are you on?

Options:

A.

Report Program Performance

B.

Monitor and Control Program Scope

C.

Monitor and Control Program Schedule

D.

Monitor and Control Program Performance

Question 40

You are the program manager for your organization and are working with Tracy, one of the project managers in your program. Tracy is having some trouble understanding the concept of the critical path in her project's network diagram. Which one of the following is the best definition of the critical path?

Options:

A.

It is the path that carries the most risk of project failure.

B.

It is the path that reveals the earliest date the project can finish.

C.

It is the path with the most important activities in the project.

D.

It is the duration of all the project activities if the labor is summed.