Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Last Attempt PgMP Questions

Page: 9 / 17
Total 452 questions

Program Management Professional (PgMP) Questions and Answers

Question 33

You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent

$789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule. Based on this information, what is the schedule variance (SV) of this program?

Options:

A.

-$85,230

B.

$821,065

C.

-$284,100

D.

-$117,295

Question 34

Several issues are identified on one component project in a program. During a meeting with that component’s project manager, the program manager offers several suggested resolutions. Two weeks later, they meet again to review progress. The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule.

What should the program manager do?

Options:

A.

Join project-level issue resolution meetings to accelerate the decision-making process.

B.

Initiate discussions with the program governance board about assigning a more experienced project manager to the project.

C.

Emphasize that the project manager needs to address the issues and follow up at the next scheduled meeting.

D.

Develop an immediate corrective action plan with the project manager and coach them on decision-making responsibilities.

Question 35

What should a program manager do when a scope change has been approved that will drastically affect the program costs assuming that the costs will be added to the program budget?

Options:

A.

Adjust the cost baseline

B.

Communicate cost of the change to all stakeholders

C.

Adjust the quality baseline

D.

Communicate the change to all stakeholders

Question 36

Which one of the following is not an output of the direct and manage program execution process?

Options:

A.

Results of program work

B.

Program budget

C.

Change requests

D.

Request to terminate the program

Page: 9 / 17
Total 452 questions