Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Online CPIM-MPR Questions Video

Page: 2 / 4
Total 105 questions

Certified in Production and Inventory Management - Master Planning of Resources Questions and Answers

Question 5

The question below is based on the following distribution requirements plan:

Lead time is 1 week, lot size is 30, and safety stock is 0. Planned order releases would occur in which of the following sequences?

Options:

A.

Weeks 3, 4, 6

B.

Weeks 2, 3, 5

C.

Weeks 2, 3, 4

D.

Weeks 3, 4, 5

Question 6

Which of the following factors should be considered when evaluating a master production schedule change?

Options:

A.

Capacity requirements plan

B.

Critical ratio of planned orders

C.

Load for key work centers

D.

Bill of material accuracy

Question 7

Which of the following items is required for making realistic customer promises?

Options:

A.

Feasible master schedules

B.

Procedures for managing abnormal demand

C.

Finished-goods safety stock

D.

A sales and operations planning process

Question 8

A firm uses the level production planning approach to produce a product family to stock. Senior management has requested that the finished-goods inventory for the product family be reduced by 18% over the sales and operations planning horizon. Which of the following statements best describes the relationship between total demand and total production required for the product family over the planning horizon?

Options:

A.

Total production required and demand will be equal.

B.

Total production required will be less than total demand.

C.

Total production required will be greater than total demand.

D.

There is not sufficient data to determine the relationship.

Page: 2 / 4
Total 105 questions