Free C_TS413_2020 SAP Updates

SAP Certified Application Associate - SAP S/4HANA Asset Management Questions and Answers

Question 5

You want to set up a scenario for regular maintenance. The first event should take place after 1 year; after that, it is a regular cycle of 6 months. Which parameter do you have to use to map this in thesystem?

Options:

A.

Shift factor

B.

Maintenance plan category

C.

Maintenance package offset

D.

Scheduling indicator

Question 6

You want to assign components to an equipment task list. There isno BOM assigned to the equipment. What is the prerequisite for using the free assignment of material?

Options:

A.

Free assignment of material is always possible without any prerequisites.

B.

Assign the header material of a material BOM to the equipmenttask list header.

C.

Assign the header material of a material BOM as assembly to atask list operation.

D.

Assign the BOM usage for free assignment of material in Customizing.

Question 7

During the implementation project you need to define the organizational units relevant for Plant Maintenance. Which of the following objects can you directly assign to a maintenance plant? Note: There are 2 correct answers to this question.

Options:

A.

Storage location

B.

Maintenance work center

C.

Business partner

D.

Maintenance planner group

Question 8

Which of the following BOMs we use to set up spare parts planning of functional locations

Options:

A.

Maintenance BOM

B.

Costing BOM

C.

construction BOM

D.

Production BOM