Question 41

A team has completed a sprint and intends to deploy these changes after business approval, but they will immediately begin the next sprint.

What strategy should an architect recommend?

Options:

A.

The first task of the new sprint must be the deployment approval. After that, the other tasks of the sprint can be performed in the environments and Git.

B.

Using Git, create a release branch from the develop branch. All fixes must be made in the release branch. After deployment, merge release with develop.

C.

Commit upcoming changes to the features branch without merging into the develop branch. Deploy from the develop branch and then merge new sprint features into the develop branch.

D.

Migrate the current code to the UAT sandbox. Begin new sprint development in the Dev sandbox. Make fixes in the UAT environment and deploy UAT for production after business approval.

Question 42

Universal Containers CUC) has multiple teams working on different projects. Multiple projects will be deployed to many production orgs. During code reviews, the architect finds inconsistently named variables and lack of best practices.

What should an architect recommend to improve consistency?

Options:

A.

Create a Center of Excellence for release management.

B.

Require pull requests to be reviewed by two developers before merging.

C.

Use static code analysis to enforce coding standards.

D.

Execute regression testing before code can be committed.

Question 43

Universal Containers is building a new complex integration to a legacy system. the legacy system is also going through a major upgrade. Senior leadership has committed to the board that the combined programs will be completed on time. What is the risk with this plan?

Options:

A.

The deadline is scheduled during a Salesforce release

B.

The project team has decided to use the Waterfall methodology

C.

The legacy system team is using an Agile methodology

D.

Multiple work -streams with dependencies could impact the go-live

Question 44

Universal Containers (UC) has been using Salesforce Sales Cloud for many years

following a highly customized, single-org strategy with great success so far.

What two reasons can justify a change to a multi-org strategy?

Choose 2 answers

Options:

A.

UC is launching a new line of business with independent processes and adding any new feature to it is too complex.

B.

UC wants to use Chatter for collaboration among different business units and stop working in silos.

C.

UC follows a unification enterprise architecture operating model by having orgs with the same processes implemented foreach business unit.

D.

Acquired company that has its own Salesforce org and operates in a different business with its own set of regulatory requirements.