CCMP Questions Bank

Page: 9 / 11
Total 150 questions

Certified Change Management Professional Questions and Answers

Question 33

You are the change agent for the public relations department that is revamping its communication strategy for transition to the future state of change within your organization. What is a key consideration in the development of your communication strategy to achieve a successful change effort?

Options:

A.

The current communication channels, tools and methods

B.

The change charter and outlined risks

C.

The organizational maturity and past change success

D.

The benefit realization and execution plan

Question 34

Who is responsible for ensuring the outputs of the lessons learned session are applied to future change projects?

Options:

A.

A project team member

B.

The project sponsor

C.

An external party (for independent perspective)

D.

The change management lead

Question 35

The vice president of marketing is the sponsor for a major change initiative. She recently accepted a new assignment in the international customer care organization and is leaving the vice president of marketing position. No replacement has been named. What is the potential project impact caused by losing a sponsor?

Options:

A.

Impact to vision and direction

B.

Reworking of the stakeholder engagement plan

C.

Potential change in benefits realization

D.

Loss of momentum until a replacement is found

Question 36

What document does a change management team develop to ensure senior executives are actively involved and visibly participating throughout the change initiative?

Options:

A.

Learning and development plan

B.

Stakeholder analysis

C.

Change management plan

D.

Sponsorship plan

Page: 9 / 11
Total 150 questions