C2010-555 Premium Exam Questions

Page: 2 / 5
Total 144 questions

IBM Maximo Asset Management v7.6 Functional Analyst Questions and Answers

Question 5

A company wishes to configure Maximo so that meter readings automatically create work orders based on condition monitoring points. The company has already configured the system in Organizational settings and created the appropriate condition monitoring points.

What additionally needs to be configured for this be accomplish?

Options:

A.

Any meter should be added to the asset and the ConditionMonWoGenCronTask should be active e

B.

A continuous type meter should be added to an asset and the PMWOGenCronTask should be active.

C.

A gauge type meter should be added to an asset and the MeasurePointWoGenCronTask should be active.

D.

A characteristic type meter should be added to an asset and the ConditionMonWoGenCronTask should be active.

Question 6

What costing method should be used if the receipt cost of items that are the oldest in stock is required?

Options:

A.

LIFO

B.

FIFO

C.

Average

D.

Standard

Question 7

A company has decided to discontinue the use of job plan revisioning. What application is used to accomplish this?

Options:

A.

Job Plans

B.

Organizations

C.

System Properties

D.

Application Designer

Question 8

Which statement is true about routes?

Options:

A.

A route can only be applied to a work order by a PM.

B.

A route's sequence numbers are fixed after it is activated.

C.

A route can create work orders for locations or assets, not both.

D.

Route Stops that become work order tasks cannot have job plans.

Page: 2 / 5
Total 144 questions