Question 5

BUSINESS CASE

Here are three statements related to the ‘business case’ practice.

In which management product should each statement be recorded?

Choose only ONE management product for each statement. Each management product can be used once, more than once, or not at all.

Options:

A.

Business case

B.

Benefits management approach

C.

Sustainability management approach

D.

End stage report

E.

Project brief

F.

Commercial management approach

Statement 1:

The project will use a linear-sequential delivery method, and a reputable external supplier will deliver most of the specialist work.

Statement 2:

One sustainability target is to reduce the number of visitors arriving in internal-combustion vehicles. The Chief Technology Officer will implement monitoring technology, and the Business Opportunities Director will

Question 6

During initiation, new information from BuildyBrick shows that additional protection of historic buildings will extend the planned duration.

Which role should the project manager consult to check that the revised plan still meets the needs of the project board and business?

Options:

A.

Business layer

B.

Team manager

C.

Project assurance

D.

Project executive

Question 7

While preparing the project plan, the project manager and BuildyBrick’s planning specialist use the product flow and data from previous projects to determine that the utilities and systems can be delivered in parallel as separate work packages.

Is this an appropriate application of the ‘plans’ practice, and why?

Options:

A.

Yes, because data from previous projects should determine the schedule without reviewing the dependencies between the products

B.

Yes, because product dependencies determine sequence, and independent work packages may be planned to run in parallel

C.

No, because work delivered by the same supplier must be scheduled sequentially and should avoid running in parallel

D.

No, because setting work-package tolerances determines the order in which products must be produced

Question 8

During the ‘starting up a project’ process, the project team decides that the complex LouisShopping infrastructure project will use a traditional, linear-sequential delivery method.

Which role is accountable for selecting the project approach?

Options:

A.

Business layer

B.

Project executive

C.

Project manager

D.

Senior supplier