Question 13

During stage 2, the project board agrees that the underground car park should contain 15 rapid-charging spaces, with a scope tolerance permitting delivery of no fewer than 10 spaces. The project manager includes this tolerance in the relevant work package agreed with the team manager.

Is this an appropriate application of the ‘manage by exception’ principle, and why?

Options:

A.

Yes, because establishing a minimum and a preferred number of charging bays creates a defined scope tolerance that enables the design team to work within an agreed range without needing to escalate every individual design decision

B.

Yes, because specifying a minimum and a preferred number of charging bays constitutes a quality tolerance that the design team must meet within the agreed work package

C.

No, because the precise number of electric charging bays to be included should be fully specified in the product description for the underground car park rather than treated as a tolerance

D.

No, because the project board should approve the precise number of charging spaces rather than delegate a permissible range to the design team

Question 14

PLANS

Here are three items of information included in the stage 2 plan.

Under which heading (A–F) should each item be recorded?

Choose only ONE heading for each item of information. Each heading may be used once, more than once, or not at all.

Options:

A.

Dependencies

B.

Planning assumptions and prerequisites

C.

Products to be delivered

D.

Budget

E.

Tolerances

F.

Monitoring, control and reporting arrangements

Item 1:

The plan assumes that limited familiarity with new sustainable technologies will increase the likelihood of design errors, so additional time has been allowed for quality control.

Item 2:

During stage 2, the project manager will send the project board a summary of design progress every two weeks.

Item 3:

Stage 2 will produce archi

Question 15

During the ‘initiating a project’ process, the team expects local heritage-protection groups to oppose the proposal. The Heritage Director suggests waiting until the groups contact the project. Instead, the project manager asks the Heritage Manager to identify groups known from previous work, and the manager supplies a list.

Is this an appropriate approach to leading successful change, and why?

Options:

A.

Yes, because the project manager is using existing stakeholder knowledge to identify affected and influential groups proactively

B.

Yes, because identifying a stakeholder guarantees that the stakeholder will support the project and its business case

C.

No, because stakeholder identification should not take place during project initiation

D.

No, because early identification of an opposing group will necessarily increase its opposition

Question 16

During ‘closing a project’, the project manager updates the arrangements that specify how and when the Head of the Portfolio Office will measure the increase in business opportunities after LouisShopping enters operational use.

During which closing activity should this be done?

Options:

A.

Prepare planned closure

B.

Confirm project acceptance

C.

Evaluate the project

D.

Request project closure