During stage 2, the project board agrees that the underground car park should contain 15 rapid-charging spaces, with a scope tolerance permitting delivery of no fewer than 10 spaces. The project manager includes this tolerance in the relevant work package agreed with the team manager.
Is this an appropriate application of the ‘manage by exception’ principle, and why?
PLANS
Here are three items of information included in the stage 2 plan.
Under which heading (A–F) should each item be recorded?
Choose only ONE heading for each item of information. Each heading may be used once, more than once, or not at all.
During the ‘initiating a project’ process, the team expects local heritage-protection groups to oppose the proposal. The Heritage Director suggests waiting until the groups contact the project. Instead, the project manager asks the Heritage Manager to identify groups known from previous work, and the manager supplies a list.
Is this an appropriate approach to leading successful change, and why?
During ‘closing a project’, the project manager updates the arrangements that specify how and when the Head of the Portfolio Office will measure the increase in business opportunities after LouisShopping enters operational use.
During which closing activity should this be done?