Question 9

A new law requires everyone working on public-infrastructure projects to hold an appropriate security clearance. The project manager records the legislation as an external event in the issue register so that its effects can be assessed.

Is this an appropriate application of the issues practice, and why?

Options:

A.

Yes, because the legislation may affect the resources available to deliver the project

B.

Yes, because external events must be managed outside the project’s agreed controls

C.

No, because legislation should be recorded after its full effect on delivery is known

D.

No, because external events are managed by the business rather than by the project team

Question 10

Before a BuildyBrick subcontractor begins testing the utilities and systems, the proposed team plan and the commitment to deliver the testing work package must be agreed.

Which role agrees to carry out the work package in the ‘managing product delivery’ process?

Options:

A.

Project manager

B.

Team manager

C.

Senior supplier

D.

Project support

Question 11

The City Council asks the portfolio office, independently of the LouisShopping project team, to provide confidence that the design and build will preserve the historic setting while incorporating the required technology.

Is this an appropriate application of the quality practice, and why?

Options:

A.

Yes, because the portfolio office should manage the project’s quality-control activities on behalf of the project manager

B.

Yes, because the business layer may use the portfolio office to perform independent quality-assurance activity on its behalf

C.

No, because assurance information may be provided to the project board and not to the business layer

D.

No, because a portfolio office may assess strategy but may not review the delivery of individual projects

Question 12

During stage 2, the Heritage Director, acting as senior user, reviews the design and raises a concern that the previously requested heritage trail has not been addressed.

Is this an appropriate use of the ‘give ongoing direction’ activity, and why?

Options:

A.

Yes, because a project board member may raise concerns and provide ongoing direction within the authority delegated to the board

B.

Yes, because the senior user has an obligation to formally approve key specialist products produced during stages 2 and 3 as a standard action within the ‘give ongoing direction’ activity

C.

No, because the ‘give ongoing direction’ activity is only triggered when the project manager proactively requests a review by the project board, not when individual board members identify concerns independently

D.

No, because the Heritage Director should first seek the agreement of the full project board before raising individual concerns, to ensure a unified project board position is presented to the project manager