Month End Sale Special - 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: big75certs

Free and Premium PRINCE2 PRINCE2-7-Practitioner Dumps Questions Answers

PRINCE2 Project Management Practitioner (Version 7) Questions and Answers

Question 1

During stage 3, several BuildyBrick subcontractors are working on different work packages. The project manager is concerned that lessons identified by one team will not reach the others and could lead to rework, delay or additional cost. The project manager therefore holds a fortnightly cross-team ‘lunch and learn’ session.

Is this an appropriate application of the ‘learn from experience’ principle, and why?

Options:

A.

Yes, because the regular knowledge-sharing sessions provide a structured mechanism for team managers to identify and apply lessons arising during the current stage

B.

Yes, because the subcontractors are expected to contribute lessons from previous construction projects that are directly relevant to the current stage

C.

No, because subcontractors should concentrate on meeting their work package commitments and tolerances rather than attending sessions that take them away from delivery

D.

No, because the Regeneration Manager should gather lessons through individual interviews with team managers and document them formally in a lessons report at the end of the stage

Buy Now
Question 2

During initiation, the project executive asks the project manager to evaluate a credible business option that omits the underground car park. The project manager includes an investment appraisal of that option in the full business case, despite the main contractor’s objection.

Is this an appropriate application of the business case practice, and why?

Options:

A.

Yes, because developing the business case includes comparing credible business options to select the most appropriate investment

B.

Yes, because customer and supplier organizations must always maintain completely separate project business cases regardless of the given investment

C.

No, because a requirement in the initial scope may never be tested as part of an alternative option

D.

No, because anticipated parking income means that no alternative should be assessed

Question 3

The stage 4 inspections cannot start because a geological survey is late. Although the survey team is generally qualified, it lacks a specific technical capability needed to complete the survey. Without first assessing the gap, the project manager recommends replacing the entire team with a subcontractor, which would cause a significant further delay.

Is this an appropriate approach to leading a successful team, and why?

Options:

A.

Yes, because bringing in a replacement subcontractor with the necessary technical skills will enable stage 4 activities to resume and reduce the risk of further delays to the overall project

B.

Yes, because the project manager has the authority to source a subcontractor when an existing team member lacks the technical competence required for their assigned work package

C.

No, because before recommending full team replacement the project manager should first seek to understand the nature of the competency gap and explore support options

D.

No, because the project manager and the survey team manager jointly developed and agreed the terms of the work package, and replacing the team contradicts the co-created ways of working

Question 4

In stage 4, work is late because the survey and utilities teams have not shared information needed by other teams, and morale is falling. The project manager considers a short weekly coordination forum for questions and information sharing, but rejects it solely because it would take time away from delivery.

Is this an appropriate approach to leading a successful team, and why?

Options:

A.

Yes, because the primary responsibility for improving team morale and overall productivity rests with each individual team manager, not the project manager

B.

Yes, because requiring team managers to attend regular coordination meetings diverts their time away from completing their work packages, thereby risking further delays

C.

No, because the project manager should create mechanisms that strengthen coordination and relationships across the project team

D.

No, because the project manager should formally escalate the missed work package deadlines to the project board via an exception report rather than attempting to resolve the issue through coordination meetings

Question 5

BUSINESS CASE

Here are three statements related to the ‘business case’ practice.

In which management product should each statement be recorded?

Choose only ONE management product for each statement. Each management product can be used once, more than once, or not at all.

Options:

A.

Business case

B.

Benefits management approach

C.

Sustainability management approach

D.

End stage report

E.

Project brief

F.

Commercial management approach

Statement 1:

The project will use a linear-sequential delivery method, and a reputable external supplier will deliver most of the specialist work.

Statement 2:

One sustainability target is to reduce the number of visitors arriving in internal-combustion vehicles. The Chief Technology Officer will implement monitoring technology, and the Business Opportunities Director will

Question 6

During initiation, new information from BuildyBrick shows that additional protection of historic buildings will extend the planned duration.

Which role should the project manager consult to check that the revised plan still meets the needs of the project board and business?

Options:

A.

Business layer

B.

Team manager

C.

Project assurance

D.

Project executive

Question 7

While preparing the project plan, the project manager and BuildyBrick’s planning specialist use the product flow and data from previous projects to determine that the utilities and systems can be delivered in parallel as separate work packages.

Is this an appropriate application of the ‘plans’ practice, and why?

Options:

A.

Yes, because data from previous projects should determine the schedule without reviewing the dependencies between the products

B.

Yes, because product dependencies determine sequence, and independent work packages may be planned to run in parallel

C.

No, because work delivered by the same supplier must be scheduled sequentially and should avoid running in parallel

D.

No, because setting work-package tolerances determines the order in which products must be produced

Question 8

During the ‘starting up a project’ process, the project team decides that the complex LouisShopping infrastructure project will use a traditional, linear-sequential delivery method.

Which role is accountable for selecting the project approach?

Options:

A.

Business layer

B.

Project executive

C.

Project manager

D.

Senior supplier

Question 9

A new law requires everyone working on public-infrastructure projects to hold an appropriate security clearance. The project manager records the legislation as an external event in the issue register so that its effects can be assessed.

Is this an appropriate application of the issues practice, and why?

Options:

A.

Yes, because the legislation may affect the resources available to deliver the project

B.

Yes, because external events must be managed outside the project’s agreed controls

C.

No, because legislation should be recorded after its full effect on delivery is known

D.

No, because external events are managed by the business rather than by the project team

Question 10

Before a BuildyBrick subcontractor begins testing the utilities and systems, the proposed team plan and the commitment to deliver the testing work package must be agreed.

Which role agrees to carry out the work package in the ‘managing product delivery’ process?

Options:

A.

Project manager

B.

Team manager

C.

Senior supplier

D.

Project support

Question 11

The City Council asks the portfolio office, independently of the LouisShopping project team, to provide confidence that the design and build will preserve the historic setting while incorporating the required technology.

Is this an appropriate application of the quality practice, and why?

Options:

A.

Yes, because the portfolio office should manage the project’s quality-control activities on behalf of the project manager

B.

Yes, because the business layer may use the portfolio office to perform independent quality-assurance activity on its behalf

C.

No, because assurance information may be provided to the project board and not to the business layer

D.

No, because a portfolio office may assess strategy but may not review the delivery of individual projects

Question 12

During stage 2, the Heritage Director, acting as senior user, reviews the design and raises a concern that the previously requested heritage trail has not been addressed.

Is this an appropriate use of the ‘give ongoing direction’ activity, and why?

Options:

A.

Yes, because a project board member may raise concerns and provide ongoing direction within the authority delegated to the board

B.

Yes, because the senior user has an obligation to formally approve key specialist products produced during stages 2 and 3 as a standard action within the ‘give ongoing direction’ activity

C.

No, because the ‘give ongoing direction’ activity is only triggered when the project manager proactively requests a review by the project board, not when individual board members identify concerns independently

D.

No, because the Heritage Director should first seek the agreement of the full project board before raising individual concerns, to ensure a unified project board position is presented to the project manager

Question 13

During stage 2, the project board agrees that the underground car park should contain 15 rapid-charging spaces, with a scope tolerance permitting delivery of no fewer than 10 spaces. The project manager includes this tolerance in the relevant work package agreed with the team manager.

Is this an appropriate application of the ‘manage by exception’ principle, and why?

Options:

A.

Yes, because establishing a minimum and a preferred number of charging bays creates a defined scope tolerance that enables the design team to work within an agreed range without needing to escalate every individual design decision

B.

Yes, because specifying a minimum and a preferred number of charging bays constitutes a quality tolerance that the design team must meet within the agreed work package

C.

No, because the precise number of electric charging bays to be included should be fully specified in the product description for the underground car park rather than treated as a tolerance

D.

No, because the project board should approve the precise number of charging spaces rather than delegate a permissible range to the design team

Question 14

PLANS

Here are three items of information included in the stage 2 plan.

Under which heading (A–F) should each item be recorded?

Choose only ONE heading for each item of information. Each heading may be used once, more than once, or not at all.

Options:

A.

Dependencies

B.

Planning assumptions and prerequisites

C.

Products to be delivered

D.

Budget

E.

Tolerances

F.

Monitoring, control and reporting arrangements

Item 1:

The plan assumes that limited familiarity with new sustainable technologies will increase the likelihood of design errors, so additional time has been allowed for quality control.

Item 2:

During stage 2, the project manager will send the project board a summary of design progress every two weeks.

Item 3:

Stage 2 will produce archi

Question 15

During the ‘initiating a project’ process, the team expects local heritage-protection groups to oppose the proposal. The Heritage Director suggests waiting until the groups contact the project. Instead, the project manager asks the Heritage Manager to identify groups known from previous work, and the manager supplies a list.

Is this an appropriate approach to leading successful change, and why?

Options:

A.

Yes, because the project manager is using existing stakeholder knowledge to identify affected and influential groups proactively

B.

Yes, because identifying a stakeholder guarantees that the stakeholder will support the project and its business case

C.

No, because stakeholder identification should not take place during project initiation

D.

No, because early identification of an opposing group will necessarily increase its opposition

Question 16

During ‘closing a project’, the project manager updates the arrangements that specify how and when the Head of the Portfolio Office will measure the increase in business opportunities after LouisShopping enters operational use.

During which closing activity should this be done?

Options:

A.

Prepare planned closure

B.

Confirm project acceptance

C.

Evaluate the project

D.

Request project closure