During stage 3, several BuildyBrick subcontractors are working on different work packages. The project manager is concerned that lessons identified by one team will not reach the others and could lead to rework, delay or additional cost. The project manager therefore holds a fortnightly cross-team ‘lunch and learn’ session.
Is this an appropriate application of the ‘learn from experience’ principle, and why?
During initiation, the project executive asks the project manager to evaluate a credible business option that omits the underground car park. The project manager includes an investment appraisal of that option in the full business case, despite the main contractor’s objection.
Is this an appropriate application of the business case practice, and why?
The stage 4 inspections cannot start because a geological survey is late. Although the survey team is generally qualified, it lacks a specific technical capability needed to complete the survey. Without first assessing the gap, the project manager recommends replacing the entire team with a subcontractor, which would cause a significant further delay.
Is this an appropriate approach to leading a successful team, and why?
In stage 4, work is late because the survey and utilities teams have not shared information needed by other teams, and morale is falling. The project manager considers a short weekly coordination forum for questions and information sharing, but rejects it solely because it would take time away from delivery.
Is this an appropriate approach to leading a successful team, and why?
BUSINESS CASE
Here are three statements related to the ‘business case’ practice.
In which management product should each statement be recorded?
Choose only ONE management product for each statement. Each management product can be used once, more than once, or not at all.
During initiation, new information from BuildyBrick shows that additional protection of historic buildings will extend the planned duration.
Which role should the project manager consult to check that the revised plan still meets the needs of the project board and business?
While preparing the project plan, the project manager and BuildyBrick’s planning specialist use the product flow and data from previous projects to determine that the utilities and systems can be delivered in parallel as separate work packages.
Is this an appropriate application of the ‘plans’ practice, and why?
During the ‘starting up a project’ process, the project team decides that the complex LouisShopping infrastructure project will use a traditional, linear-sequential delivery method.
Which role is accountable for selecting the project approach?
A new law requires everyone working on public-infrastructure projects to hold an appropriate security clearance. The project manager records the legislation as an external event in the issue register so that its effects can be assessed.
Is this an appropriate application of the issues practice, and why?
Before a BuildyBrick subcontractor begins testing the utilities and systems, the proposed team plan and the commitment to deliver the testing work package must be agreed.
Which role agrees to carry out the work package in the ‘managing product delivery’ process?
The City Council asks the portfolio office, independently of the LouisShopping project team, to provide confidence that the design and build will preserve the historic setting while incorporating the required technology.
Is this an appropriate application of the quality practice, and why?
During stage 2, the Heritage Director, acting as senior user, reviews the design and raises a concern that the previously requested heritage trail has not been addressed.
Is this an appropriate use of the ‘give ongoing direction’ activity, and why?
During stage 2, the project board agrees that the underground car park should contain 15 rapid-charging spaces, with a scope tolerance permitting delivery of no fewer than 10 spaces. The project manager includes this tolerance in the relevant work package agreed with the team manager.
Is this an appropriate application of the ‘manage by exception’ principle, and why?
PLANS
Here are three items of information included in the stage 2 plan.
Under which heading (A–F) should each item be recorded?
Choose only ONE heading for each item of information. Each heading may be used once, more than once, or not at all.
During the ‘initiating a project’ process, the team expects local heritage-protection groups to oppose the proposal. The Heritage Director suggests waiting until the groups contact the project. Instead, the project manager asks the Heritage Manager to identify groups known from previous work, and the manager supplies a list.
Is this an appropriate approach to leading successful change, and why?
During ‘closing a project’, the project manager updates the arrangements that specify how and when the Head of the Portfolio Office will measure the increase in business opportunities after LouisShopping enters operational use.
During which closing activity should this be done?