During the ‘initiating a project’ process, the team expects local heritage-protection groups to oppose the proposal. The Heritage Director suggests waiting until the groups contact the project. Instead, the project manager asks the Heritage Manager to identify groups known from previous work, and the manager supplies a list.
Is this an appropriate approach to leading successful change, and why?
During initiation, new information from BuildyBrick shows that additional protection of historic buildings will extend the planned duration.
Which role should the project manager consult to check that the revised plan still meets the needs of the project board and business?
BUSINESS CASE
Here are three statements related to the ‘business case’ practice.
In which management product should each statement be recorded?
Choose only ONE management product for each statement. Each management product can be used once, more than once, or not at all.