Winter Sale - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Free and Premium Exin CDCS Dumps Questions Answers

Page: 1 / 9
Total 120 questions

EXIN EPI Certified Data Centre Specialist Questions and Answers

Question 1

Racks with 1.0 m depth and cold aisle containment with 3 perforated tiles are used. What aisle pitch is recommended?

Options:

A.

5 tiles pitch rule

B.

7 tiles pitch rule

C.

8 tiles pitch rule

D.

10 tiles pitch rule

Buy Now
Question 2

When designing a data center network, your company wants to minimize the number of network switches to manage.

What type of physical cabling layout would be the best choice?

Options:

A.

ToR (Top of Rack) design

B.

EoR (End of Row) design

C.

Star network design using coaxial cables

D.

It does not matter as the number of switches is not influenced by the physical cabling layout

Question 3

When are the wet bulb and dry bulb temperatures identical?

Options:

A.

When the dry bulb's temperature is at the lowest allowable temperature for IT equipment as per ASHRAE

B.

When the dry bulb's temperature is at the highest allowable temperature for IT equipment as per ASHRAE

C.

When the relative humidity is at the best practice value for relative humidity, being 50% RH

D.

When the relative humidity is 100%

Question 4

What is the floor loading requirement for a Rated-3 data center according to ANSI/TIA-942?

Options:

A.

7.2 kPa

B.

8.4 kPa

C.

12 kPa

D.

15 kPa

Question 5

A data center is located in an area where the demand for power is higher than the utility power company is able to deliver. This results in frequent power outages and, therefore, power shedding (scheduled/controlled power shutdown for areas) is frequently applied. The mains power is more than 650 hours/year not available.

What type of generators should be installed?

Options:

A.

Standby generators should be installed in at least an N+1 configuration

B.

Continuous generators should be installed, at least in an N+1 configuration

C.

A combination of standby-, prime-, and continuous-generators, as the duration of the power outage is unpredictable. The total available capacity of the generators should be at least 500% of the data center load

D.

Continuous generators should be installed; no N+1 configuration is needed as the generators will run all the time

Question 6

The pipes of a VESDA smoke detection system are installed at the air intake of the air conditioner inside the computer room.

Is this a good practice from an early smoke detection point of view?

Options:

A.

It depends on the type of gas-based fire suppression which will be installed.

B.

Yes, as this reduces the amount of piping to be installed in the data center, as all air will go through the air conditioner.

C.

No, the piping should be installed at the air exhaust of the air conditioner, as there can also be a fire inside the air conditioner itself.

D.

No, it will give a longer reaction time for the smoke detection system and there might also be bypass airflow.

Question 7

What is a disadvantage of hypoxic-based fire suppression?

Options:

A.

Only usable in non-occupied areas

B.

Only usable in rooms with sufficient air changes

C.

Gas containers must be close to hazard

D.

Only usable with positive pressure rooms

Question 8

What is forced entry resistance based on?

Options:

A.

Time, tools, and people

B.

Rate and installed number of CCTV cameras

C.

Building materials used and the location of the data center

D.

The number of security guards on duty

Question 9

A sprinkler system employs automatic sprinklers attached to a piping system containing water and connected to a water supply so that water discharges immediately when a head opens. What is this called?

Options:

A.

Dry pipe system

B.

Deluge system

C.

Pre-action system

D.

Wet pipe system

Question 10

The electrical diagram of the data center shows the following UPS configuration and has a load of 80 kW.

What is the set-up in this data center?

Options:

A.

2+N+1

B.

2(N+1)

C.

N+N(+1)

D.

(N+1)-(N+1)

Question 11

You are installing new copper cabling.

What is the advantage or disadvantage of choosing pre-terminated category 6 or 6A cabling?

Options:

A.

Pre-terminated cabling is already factory tested and saves installation time.

B.

There is no advantage as most new copper cabling network designs are based on category 3 or 5E for horizontal cabling.

C.

Pre-terminated cabling has a higher fire rating.

D.

Pre-terminated cabling makes ordering of the copper cables more complex, as you need to know in advance on which side the male or female connector needs to be located.

Question 12

Maximum exposed area of fire-rated glass is 2 m², but the window is 5 m². What is the best option?

Options:

A.

Replace with normal glass

B.

Split into two equal parts with silicone

C.

Split into two equal parts with aluminum frame

D.

Split into smaller parts within 2 m² using fire-rated frames

Question 13

A computer room is fitted with a hypoxic-based fire suppression system. On what principle does it work?

Options:

A.

It removes the heat from the fire

B.

It lowers the oxygen levels in the room

C.

It removes the fuel from the fire

D.

It uses water as an extinguisher

Question 14

A 5kW (power consumption) server keeps crashing with the message 'temperature too high'.

The intake temperature is measured at 25 °C/77 °F and a relative humidity (RH) level of 50%.

The exhaust temperature is 29 °C/84 °F and 45% RH.

The raised floor is providing an adequate amount of CFM/CMH at a reasonable velocity.

The pressure under the raised floor is approximately 25 Pa/0.1 inch H₂O.

Analyze the situation and indicate what the most likely cause is for this server to crash.

Options:

A.

Dust inside the server causing issues with convection-based heat transfer

B.

The exhaust temperature is exceeding the ASHRAE recommended values

C.

The raised floor pressure is too low and/or the raised floor tile % opening is not adequate

D.

No cause could be determined as the CFM/CMH of the air conditioning equipment is not stated

Question 15

An air-conditioner unit needs to be selected. Two types are available:

Unit-A has a Sensible Heat Ratio (SHR) of 0.7.

Unit-B has a Sensible Heat Ratio (SHR) of 0.9.

From an efficiency point of view, which one should be selected?

Options:

A.

It does not matter, as the Sensible Heat Ratio has nothing to do with efficiency.

B.

Not relevant, as Sensible Heat Ratio is only specified for air-conditioner equipment to indicate the ratio between intake temperature and exhaust temperature.

C.

Unit A

D.

Unit B

Question 16

The building requires sprinklers and is equipped with a wet-pipe system. What action should you recommend for the computer room?

Options:

A.

Maintain the current wet-pipe system

B.

Replace the wet-pipe system with a deluge system

C.

Replace the wet-pipe system with a pre-action system

D.

Replace the wet-pipe system with a dry-pipe system

Question 17

The UPS of a data center, with an ANSI/TIA-942 Rating-4, is installed with the rectifier connected to power feed A and the bypass/reserve line input connected to power feed B.

To which feed will the output of the UPS be synchronized?

Options:

A.

The UPS will not synchronize to any of the feeds but use an internal clock to set the output voltage and frequency

B.

Depends on the setting of the UPS, as the UPS can normally be set to either feed

C.

Feed A

D.

Feed B

Question 18

Which class of UPS is ideal for data centers?

Options:

A.

VFD (Voltage and Frequency Dependent)

B.

VI (Voltage Independent)

C.

VFI (Voltage and Frequency Independent)

D.

First class

Question 19

What is the advantage of OM5 multimode fiber cabling?

Options:

A.

Supports SWDM, requiring fewer fibers

B.

No advantage—same as OM4

C.

Designed for cheaper LED transmitters

D.

100 Gbit/s link for 500 m reach

Question 20

It is assumed that EMF shielding material must be installed as the EMF levels coming from the transformer room into the computer room are measured at 100mG. The transformer room is approximately 10 meters away from the computer room and is separated by a corridor. You can assume that no physical issues are present for installing shielding material at any area/location.

Where should you recommend the shielding material to be installed?

Options:

A.

As close as possible to the computer room

B.

As close as possible to the transformer room

C.

It does not matter, either close to the transformer room or the computer room is okay as there is no impact to cost or shielding material performance

D.

Shielding is not required to be installed as 100mG is within the acceptable levels for computer rooms

Question 21

A data center is in an area where utility power is highly available—only a few outages per year, typically <1 hour per event and <50 hours/year not available. What type of generators should be installed?

Options:

A.

Continuous generators in at least N+1

B.

A combination of standby, prime, and continuous sized to 500% of the load

C.

Standby generators; no N+1 needed as the risk of a failure to start is negligible

D.

Standby generators, ideally in an N+1 configuration

Question 22

What precaution shall be taken for cabling leading into an equipment rack when a data center is in a seismic-prone area?

Options:

A.

Cables should be loosely organized to allow for movement and be latched at the connectors.

B.

Cables shall be tightly organized to the rack and trays to avoid movement.

C.

Cables can be organized in any way as it is not important.

D.

Cables should be replaced by busbar trunking.

Question 23

What indicates the breaking capacity of a fuse or breaker?

Options:

A.

Mechanical strength of the casing of a fuse or breaker.

B.

The maximum voltage, in case of an electrical surge, that the fuse or breaker can handle without being destroyed or causing an electric damaging arc.

C.

The current at which the device will trip.

D.

The current that a fuse or breaker is able to interrupt without being destroyed or causing an electric damaging arc.

Question 24

FM-200 is phasing out as a halocarbon gas and management has decided to replace this with the more environmentally friendly Novec-1230 gas. Should you use exactly the same formula and parameters to calculate the gas content for the Novec-1230 gas?

Options:

A.

Yes, as long as the temperature in the computer room has not changed

B.

Yes, if you take the difference between the net and gross volume into account

C.

Yes, as long as you use the same units of measure (kg/m³ or lbs/ft³)

D.

Yes, if you change the S-factor of the formula to reflect the gas type used

Question 25

The location of a data center is just above the Arctic Circle (North Pole). The outside air temperature is never above 21°C/70°F.

Taking energy efficiency as the highest priority, which cooling system should you recommend?

Options:

A.

Standard air conditioning units, as spares might not be readily available

B.

Any cooling system can be efficient because the outside air temperature will not influence the temperature of the air intake of the ICT equipment

C.

Waterside economizer

D.

Airside economizer

Question 26

What mainly affects the cooling capacity of a raised floor tile?

Options:

A.

Type of ICT equipment, location of the air conditioner, pressure under the raised floor, allowable temperature in the hot aisle

B.

Relative humidity in the computer room, temperature of the cold air, pressure under the raised floor, construction material of the tile

C.

Percentage of the surface opening, obstruction of the supporting construction, pressure under the raised floor, damper construction

D.

Percentage of the surface opening, airflow direction of the ICT equipment, temperature difference between the air intake and air exhaust of the ICT equipment, construction material of the tile

Question 27

Should aerosol cleaning solutions be used in the computer room?

Options:

A.

No, unless leak detection installed

B.

No, it will contaminate the room

C.

Yes, only if room smells bad

D.

Yes, if not connected to power

Question 28

What is the main reason to install Earth Leakage protection?

Options:

A.

Protection of ICT equipment against high-frequency noise currents

B.

Protection of human lives

C.

Improvement of the data center grounding/earthing system

D.

Protection against lightning strikes

Question 29

The 'maximum exposed area' of the fire-rated glass is defined by the supplier as 3 sqm/32 sqft. The window area is 4 sqm/43 sqft.

What would be the best option?

Options:

A.

Do not use fire-rated glass due to the size limit and replace it with normal glass.

B.

Split the window in two equal parts using an aluminum frame.

C.

Split the window into parts smaller than specified as the maximum exposed area and ensure fire-rated frames are used.

D.

Split the window in two equal parts fitted together with transparent silicon glue.

Question 30

Do you need to consider bullet (ballistic) protection when designing a data center?

Options:

A.

No; bullet protection is not a requirement of ANSI/TIA-942

B.

No, there is no reason for implementing bullet protection as you cannot predict the type of weapons that might be used

C.

Yes, but only when the data center is built in an area with a high criminality rate or with a risk of terrorist attacks

D.

Yes, bullet protection is a requirement of ANSI/TIA-942 for Rated-3/4 data centers

Question 31

Do all residual current devices (RCDs) use the same operating principle?

Options:

A.

Yes, they all detect current differences on live and neutral wire

B.

Yes, they all measure voltage on the earth conductor

C.

No, ELCB measures earth voltage, whereas RCD detects current differences

D.

No, depending on regulations some use thermal-magnetic operation

Question 32

Does hot/cold aisle containment impact PUE?

Options:

A.

Yes, but not with cooling towers

B.

Yes, avoidance of mixing improves PUE

C.

No, airflow has no impact on power

D.

No, unless using virtualization

Question 33

What is the minimum requirement for power feeds to a Rated-4 data center (ANSI/TIA-942)?

Options:

A.

Two feeds from two different substations, one power company not acceptable

B.

Two feeds from two different substations, one power company acceptable

C.

Two feeds from one substation

D.

One feed split into two distribution boards

Question 34

Which of the following statements is correct?

Options:

A.

With current increasing, single-phase cables emit more EMF than three-phase cables

B.

With current decreasing, three-phase cables emit more EMF than single-phase cables

C.

With voltage increasing, single-phase cables emit more EMF than three-phase cables

D.

With voltage decreasing, three-phase cables emit more EMF than single-phase cables

Question 35

What is the effect of having a damper (in open position) construction in a raised-floor tile?

Options:

A.

Dampers allow for a higher supply air temperature

B.

Dampers increase the air volume by approximately 10%

C.

Dampers reduce the air volume by approximately 10%

D.

Dampers can be used when there is a high rate of temperature change in the computer room

Question 36

Do you need to consider blast protection when designing a data center?

Options:

A.

No, there is no reason for implementing blast protection as nobody can predict the impact of a bomb explosion.

B.

Yes, if the data center is a potential target or the building is located within the vicinity of (close by) a potential target.

C.

No, blast protection is not a requirement of ANSI/TIA-942.

D.

Yes, blast protection is a requirement of ANSI/TIA-942.

Page: 1 / 9
Total 120 questions