A new project being set up requires consistency across all floor plans. However, because of variations in floor-to-floor heights, the project team needs a different View Range for each level.
What is the most efficient way to accommodate this?
A government facility project requires unique data formatting and export requirements that comply with a global data-management initiative. A workflow utilizing a newly released add-on tool is developed to perform this task.
How should a BIM manager define training and ensure the appropriate staff receive it?
During an initial coordination meeting, the team agreed that the contractor will be able to mark up the latest model and sheets in Autodesk Forma every week.
Which two actions should the BIM Manager take to ensure this is implemented correctly? (Select two.)
A Revit model has become very slow for the team immediately after a regularly scheduled file distribution across all disciplines.
What two steps can the BIM manager take to review issues across the connected files? (Select two.)
The BIM manager is coordinating a multi-building project in which each building must maintain a unique internal coordinate system but share a common origin point for site-wide references.
Which two actions are required to correctly manage the coordinate setup in this scenario? (Select two.)
The BIM manager is conducting a health check of a design model submitted by a consultant to assess its readiness for coordination. Several model performance concerns have been raised, including long open times, sluggish navigation, and excessive file size.
Which of the following actions would best help to evaluate the model’s health and identify areas of improvement?
During a weekly BIM health review, the BIM manager compares two versions of the same architectural Revit model submitted one month apart. The newer model’s file size has doubled, synchronization time has increased by 40%, and users report sluggish performance. A model audit reveals no major geometry changes, but warnings have increased from 600 to 750, and several Civil CAD files are now imported.
What is the most likely root cause of the model performance degradation?
A multidisciplinary healthcare project has multiple firms contributing to a federated model. Early coordination reviews reveal data inconsistencies, unauthorized edits, and missed communication between design teams.
What is the most appropriate first step to establish effective coordination and risk mitigation across the delivery team?
The BIM manager is working on a mixed-use project in which consultants are on different platforms and delivery timelines. The client requires COBie-compliant data handover and weekly coordination uploads.
What is the best approach to ensure project-specific BIM processes are effectively implemented from the outset?
An AEC company has received a design model from the Architect of Record to begin creating construction documentation. The BIM Execution Plan identifies a fast-track delivery schedule, and the project team includes new consultants with limited exposure to the client’s preferred toolset and workflows. The BIM manager must determine how best to prepare the delivery team and assess the model’s compatibility with internal systems.
As the BIM manager prepares for the Project Kickoff meeting, which two pieces of information are most critical to avoid issues related to digital compatibility? (Select two.)
A designer needs to add Area Lines in an Area Plan, but upon adding them, they receive a message stating that none of the created elements are visible.

Where can they check to resolve the issue?
During early coordination on a hospital project, the BIM manager runs a general clash detection between all models and generates over 3,000 clash results. Many are low-priority issues, such as wall-grid overlaps and minor duct-ceiling intersections. The project’s clash matrix outlines only high-impact clashes between structural, MEP, and architecture in specific zones.
For the BIM manager, what is the most appropriate next step to align clash reporting with the project’s coordination strategy?
During a model review, several linked files appear missing or unloadable in the federated coordination file. The files were present and working the day before, and no changes were made to the Revit host model itself.
As the BIM manager, what is the most appropriate step to troubleshoot the issue?
The BIM manager receives an external lighting CAD file to link into the Architectural model and realizes the link is not vertically or horizontally aligned.
What fix needs to happen to resolve this misalignment?
For a project that is well into its Design Development phase, it is discovered that there is an easement on the property that increases the setback by 1 ft 6 in. (450 mm).
Which method for updating the geolocation of the project would be least disruptive to the extended design team?
The BIM manager on a large mixed-use development is leading the development of the project’s information-delivery strategy. The client has strict handover requirements for both asset data and spatial coordination. The design schedule includes overlapping packages, and some task teams are unfamiliar with structured data exchanges.
What is the most appropriate approach to establish the project’s information-delivery plans?
A campus project of several duplicated links of a building model has received an updated civil background, with revised GIS coordinates.
Drag and drop to indicate the correct order of steps the BIM manager should perform to revise the architectural model.
