Autodesk Certified Professional BIM_MGT_101 Passing Score

Page: 2 / 4
Total 57 questions

Autodesk Certified Professional in BIM Management for Building Design Questions and Answers

Question 5

The BIM manager is coordinating a multi-building project in which each building must maintain a unique internal coordinate system but share a common origin point for site-wide references.

Which two actions are required to correctly manage the coordinate setup in this scenario? (Select two.)

Options:

A.

Place the Survey Point at the shared site origin for all buildings.

B.

Create unique Survey and Project Base Points for all buildings, maintaining individual Building Coordination.

C.

Place the Project Base Point at the shared site origin for all buildings.

D.

Share coordinates by acquiring from the master site model, using a single Survey and Project Base Point.

E.

Assign a unique Project Base Point for each building model.

Question 6

The BIM manager is conducting a health check of a design model submitted by a consultant to assess its readiness for coordination. Several model performance concerns have been raised, including long open times, sluggish navigation, and excessive file size.

Which of the following actions would best help to evaluate the model’s health and identify areas of improvement?

Options:

A.

Run a performance audit using review tools and evaluate the number of warnings, file size, and modeling practices such as in-place families.

B.

Notify the consultant to reduce the model file size by deleting sheets and exporting only 3D views.

C.

Review the consultant’s coordination clash reports to determine if unresolved issues are impacting performance.

D.

Disable all linked files and re-enable them one at a time to identify which one is causing performance issues.

Question 7

During a weekly BIM health review, the BIM manager compares two versions of the same architectural Revit model submitted one month apart. The newer model’s file size has doubled, synchronization time has increased by 40%, and users report sluggish performance. A model audit reveals no major geometry changes, but warnings have increased from 600 to 750, and several Civil CAD files are now imported.

What is the most likely root cause of the model performance degradation?

Options:

A.

A rise in geometry complexity.

B.

An accumulation of audit history and backup data.

C.

The presence of imported Civil CAD files.

D.

The increase in model warnings.

Question 8

A multidisciplinary healthcare project has multiple firms contributing to a federated model. Early coordination reviews reveal data inconsistencies, unauthorized edits, and missed communication between design teams.

What is the most appropriate first step to establish effective coordination and risk mitigation across the delivery team?

Options:

A.

Assign responsibility for each firm to review and maintain its own models, document identified issues, and present findings during scheduled coordination meetings.

B.

Implement tighter access controls within the Common Data Environment by defining permissions, monitoring edits, and restricting changes to authorized team members.

C.

Develop and communicate protocols that clarify model ownership, editing rights, quality-control procedures, and expected communication channels.

D.

Require each discipline to submit a detailed modelling strategy, document its assumptions, and use this information to identify and resolve potential design conflicts.