During early coordination on a hospital project, the BIM manager runs a general clash detection between all models and generates over 3,000 clash results. Many are low-priority issues, such as wall-grid overlaps and minor duct-ceiling intersections. The project’s clash matrix outlines only high-impact clashes between structural, MEP, and architecture in specific zones.
For the BIM manager, what is the most appropriate next step to align clash reporting with the project’s coordination strategy?
A new project being set up requires consistency across all floor plans. However, because of variations in floor-to-floor heights, the project team needs a different View Range for each level.
What is the most efficient way to accommodate this?
A campus project of several duplicated links of a building model has received an updated civil background, with revised GIS coordinates.
Drag and drop to indicate the correct order of steps the BIM manager should perform to revise the architectural model.