Selected Prince2-Practitioner PRINCE2 Certification Questions Answers

PRINCE2 7 Practitioner (7th Edition) Exam Questions and Answers

Question 65

Which of the following statements is False regarding the Risk Management Strategy?

Options:

A.

It captures and maintains all relevant information on identified threats and opportunities

B.

It documents the risk tolerances

C.

It documents the approach to risk

D.

It identifies responsibilities towards risk for the project

Question 66

Scenario

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

Which 2 statements should be recorded under the Proximity heading?

Options:

A.

Proximity categories for this project are: Imminent; Within the stage; Within the project; Beyond the project.

B.

The risk of MFH having no outsourcing experience will be categorized as Stage 4 proximity.

C.

Imminent risks are those which may occur within two weeks.

D.

Any risk with a proximity category of imminent will be estimated as having a very high impact.

E.

The risk of staff leaving the organization will be categorized as beyond the project proximity.

Question 67

Scenario

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

Which 2 statements should be recorded under the Roles and responsibilities heading?

Options:

A.

Each risk will be assigned a risk owner.

B.

Risks exceeding the agreed project risk tolerance will be reported to the Project Board.

C.

Risk tolerances are allocated to each stage by the Project Manager.

D.

Project Assurance will ensure that project risks are identified, assessed and controlled according to the agreed risk management procedure.

E.

An external consultant is to facilitate a risk identification workshop.

Question 68

Who is responsible for reviewing the risk management practices to ensure they are in line with the project's risk management strategy?

Options:

A.

Project Support

B.

Project Manager

C.

Team Manager

D.

Project Assurance