Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PRINCE2 Prince2-Practitioner Questions Answers

PRINCE2 7 Practitioner (7th Edition) Exam Questions and Answers

Question 9

While producing the Team Plan to deliver the agreed Work Package, it became apparent that the user representatives assigned 10 check some of the products were unsuitable.

Which 2 actions should the Team Manager take in response to this situation?

Options:

A.

Consult the Senior Supplier to assign suitable reviewers.

B.

Discuss the situation with Project Assurance and agree the changes or additions to the reviewers. Advise the Project Manager of this risk.

C.

Ensure the Quality Register is updated with details of the agreed amendments to the reviewers.

D.

Notify the Project Manager by raising an Exception Report explaining that the original reviewers are unsuitable.

Question 10

During Executing a Work package, specialist products are created and quality reviews are carried out - which management product captures the details of these reviews?

Options:

A.

Team Plan

B.

Checkpoint Report

C.

Quality Register

D.

Configuration Item Record

Question 11

Which of the following statements is FALSE regarding the Continued Business Justification?

Options:

A.

The justification for the project must remain the same throughout the project

B.

The justification for the project should remain valid

C.

The justification for the project may change

D.

If the project is no longer justified it should be stopped

Question 12

Which of the following is NOT a trigger for the project manager to authorize a work package?

Options:

A.

Stage Authorization

B.

Corrective Action

C.

Exception plan approved

D.

Reporting highlights