Planning & Scheduling Professional (PSP) Exam Questions and Answers

Question 57

How many entities/subcontractors should a scheduled activity cover?

Options:

A.

More than one it the activity is in a single calendar period

B.

More than one it the subcontractors agree

C.

Only one

D.

More than one if the concurrent work cannot be split between subcontractors

Question 58

Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT

Options:

A.

Use gross building square footages. The pluses and minuses all average out.

B.

Look at each activity independently and don't follow specific logic paths when assigning activity durations.

C.

Divide activities into smaller activities. This will increase activity detail and duration estimate accuracy.

D.

Use the people responsible for performing the work as a resource to assign activity durations.

Question 59

What changes to logic would eliminate Activity B from the critical path?

Options:

A.

Replace the relationship from Activity B to Activity C with SSO

B.

Reduce the lag value of the relationship from Activity A to Activity B from 5 to 0

C.

Add a SS 15 relationship from Activity A to Activity B and replace the relationship from Activity A to Activity B with FFO

D.

Replace the relationship from Activity A to Activity B with FFO and add an FSO relationship from Activity A to Activity C

Question 60

Determine the correct formula and date for the late finish for Activity 9004.

Options:

A.

LS.10002 + 1 day -> 11-29-03.

B.

LS.10002^ Lag.7 + i day -> 11-20-03.

C.

LS.10002 - 1 day -> 11-27-03.

D.

LS.10002 - Lag.7 - l day -> 11-20-03.