Big Halloween Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Download Full Version PSP ASIS Exam

Page: 3 / 16
Total 216 questions

Planning & Scheduling Professional (PSP) Exam Questions and Answers

Question 9

Project schedules help control all of the following EXCEPT for_____________________.

Options:

A.

Quality

B.

Cost

C.

Resources

D.

Time

Question 10

Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

Options:

A.

It is calculated using the original logic.

B.

It is calculated using logic reflecting out-of-sequence progress.

C.

An out-of-sequence activity cannot resume until all predecessors are finished.

D.

There is no such thing.

Question 11

When are KPIs defined?

Options:

A.

At project initiation

B.

At NTP

C.

At the start of the Construction Phase

D.

After the Bidding Phase

Question 12

The sum of all budgets for work scheduled to be accomplished within a given time period is the ____________.

Options:

A.

Estimate at completion (EAC)

B.

Budget at completion (BAC)

C.

Budgeted cost of work performed (BCWP)

D.

Budgeted cost of work scheduled (BCWS)

Page: 3 / 16
Total 216 questions