Which statement is true?
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
Activity 2003 started during the current reporting period and proceeded as planned with the normal schedule. If the remaining duration at the end of this period is ten workdays, then what is the earned value assignable to Activity 2003 in the pay estimate for this reporting period?
Prior to the start of work, Management determined the need to make the Product available 10 workdays earlier than planned. Which activities need to be expedited?