Big Halloween Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PDF PSP Study Guide

Page: 14 / 16
Total 216 questions

Planning & Scheduling Professional (PSP) Exam Questions and Answers

Question 53

Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?

Options:

A.

11 Mar 2024

B.

21 Mar 2024

C.

19 Feb 2024

D.

20 Mar 2024

Question 54

There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?

Options:

A.

2 cranes

B.

1 crane

C.

4 cranes

D.

3 cranes

Question 55

Before the work begins, the contractor considers crashing the schedule. How much would the crashed general conditions have to be reduced to break even with the normal cost budget?

Options:

A.

$195 per day

B.

S1.772 per day

C.

General conditions do not need to be reduced to break even

D.

$1.223 per day

Question 56

Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?

Options:

A.

3.3%

B.

2.2%

C.

23%

D.

2 4%

Page: 14 / 16
Total 216 questions