Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Passed Exam Today MSP-Practitioner

MSP Practitioner, 5th edition Exam Questions and Answers

Question 17

The Customer Processes Project has reported that the work to develop the integrated billing and accounting services is progressing according to plan. However, when the system was tested, the system performance was very slow and there are errors that were not previously identified. The programme manager is concerned about the possible impact of this inaccurate reporting.

Which type of data gathering should be improved, and why?

Options:

A.

Looking back: because the project’s reporting focus should be upwards and outwards

B.

Looking back, because the project's reporting represents a risk to the overall programme delivery

C.

Looking forward, because the programme should identify emerging risks from the wider context

D.

Looking forward, because the project should inform the programme of these disruptive trends

Question 18

The programme is halfway through the first tranche. The CRO has contacted the programme manager with exciting news. They have been shown a new piece of technology which makes it easier and cheaper to service and maintain smart meters. They think that it might be possible to add this technology to future smart water meter installations without much additional cost. The programme manager has added this to the risk register.

Is this an appropriate application of the design' theme, and why?

Options:

A.

Yes, because if smart meter installations include this technology then future maintenance costs could be reduced

B.

Yes, because changing the existing installation plan could bring uncertainty to the programme and should be avoided

C.

No, because reduced maintenance costs should be added to the benefits map as a new benefit of the programme

D.

No, because the possibility of reducing maintenance costs should be treated as an issue and action taken immediately

Question 19

When approval to proceed is given at the end of Defining a Programme, what does this mean?

Options:

A.

The approval authorizes the work of all projects in the first tranche of programme.

B.

The approval authorizes the SRO to proceed with the whole programme.

C.

The approval authorizes the start of the first project in the first tranche only.

D.

The approval only acknowledges that the documents developed so far are acceptable.

Question 20

Which type of cost is associated in training, moving and supporting an operational unit?

Options:

A.

Programme management cost

B.

Capital cost

C.

Business change and transition cost

D.

Benefits realization cost