Which of below sentences best defines programme management?
The programme manager has produced a rough estimate of costs based on the recently completed roll-out of smart metered services to electricity and gas customers.
Is this an appropriate application of the ‘identify the programme' process, and why?
The programme is in the ‘design the outcomes’ process for the first time. The Research and Development Project team has recommended that UU sources an imported next generation smart meter. This is an alternative to the development of the smart meter internally. The imported meter can be fully implemented before the CEO retires in three years' time. However, there is a possibility that this meter could lead to future information security risks.
Is this recommendation an appropriate application of the ‘decisions' theme, and why?