Certified Data Center Facilities Operations Manager Questions and Answers

Question 5

What is the formula to calculate the PUE of a Data Center?

Options:

A.

PUE = UPS input power / UPS output power

B.

PUE = VA * PF

C.

PUE = Total facility power / Total IT equipment power

D.

PUE = Total generator capacity / total battery capacity

Question 6

Training programs need to be selected.

Of the below, which is the first activity to start with?

Options:

A.

Create inventory of the services in the service catalog

B.

Contact training providers requesting for brochures

C.

Review the skills matrix

D.

Compare prices of various training programs

Question 7

Maintenance needs to be outsourced; management demands a contract option with the lowest risk possible.

Which is the best option to choose?

Options:

A.

Basic/standard/non-comprehensive

B.

Time and Material

C.

Comprehensive

D.

Exclusive

Question 8

Which, of the items below, is not part of operational cost (OPEX)?

Options:

A.

Cost of staffing

B.

Replacing the fans and belts of an air-conditioner

C.

Acquisition of real estate

D.

Annual software license fees