Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

H19-311 Exam Dumps : Huawei Certified Pre-sales Associate- Data Center Facility

PDF
H19-311 pdf
 Real Exam Questions and Answer
 Last Update: Oct 19, 2025
 Question and Answers: 225
 Compatible with all Devices
 Printable Format
 100% Pass Guaranteed
$25.5  $84.99
H19-311 exam
PDF + Testing Engine
H19-311 PDF + engine
 Both PDF & Practice Software
 Last Update: Oct 19, 2025
 Question and Answers: 225
 Discount Offer
 Download Free Demo
 24/7 Customer Support
$40.5  $134.99
Testing Engine
H19-311 Engine
 Desktop Based Application
 Last Update: Oct 19, 2025
 Question and Answers: 225
 Create Multiple Test Sets
 Questions Regularly Updated
  90 Days Free Updates
  Windows and Mac Compatible
$30  $99.99

Verified By IT Certified Experts

CertsTopics.com Certified Safe Files

Up-To-Date Exam Study Material

99.5% High Success Pass Rate

100% Accurate Answers

Instant Downloads

Exam Questions And Answers PDF

Try Demo Before You Buy

Certification Exams with Helpful Questions And Answers

Huawei Certified Pre-sales Associate- Data Center Facility Questions and Answers

Question 1

When using a UPS5000-E (50 kVA power module) with the actual load of 160 kW, 1+1 rack redundancy, and single UPS backup solution, each rack uses three battery strings, each battery string consists of 40 batteries, and the main switch box capacity is ().

Options:

A.

250A

B.

320 A

C.

500 A

D.

630 A

Buy Now
Question 2

Considering that the UPS is fully configured but has a low system load rate in the initial stage, the UPS5000-E is designed with a smart hibernation function, which can improve system load rate to ensure highly efficient operation. In case of smart hibernation, how many redundant power modules does the UPS5000-E have at least?

Options:

A.

0

B.

1

C.

2

Question 3

Which of the following actions does the UPS2000-A take to deal with excessive operating temperatures?

Options:

A.

Switch to bypass mode.

B.

Switch to battery mode.

C.

Stop output and power off loads.

D.

No action is taken.