Pre-Winter Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Free and Premium Scrum SMC Dumps Questions Answers

Page: 1 / 8
Total 100 questions

Scrum Master Certified (SMC) Questions and Answers

Question 1

Scrum facilitates flexibility through transparency, inspection, and adaptation to ultimately achieve the most valuable business outcomes. All of the following characteristics of Scrum help in achieving flexibility, EXCEPT:

Options:

A.

Iterative product development

B.

Cross-functional teams

C.

Continuous stakeholder involvement

D.

Time-boxing

Buy Now
Question 2

All of the following contribute to the Daily Standup, EXCEPT:

Options:

A.

Scrum Burndown Chart

B.

Prioritized Product Backlog

C.

Product Owner

D.

Dependencies

Question 3

One of the responsibilities of the Scrum Master is to ensure that the Product Owner does not change the Acceptance Criteria of a committed User Story in the middle of a Sprint. In this regard, which of the following statements about Acceptance Criteria is correct?

Options:

A.

User Story Workshops are held as part of Sprint Review.

B.

Acceptance Criteria provide the objectivity required for the User Story to be considered Done or not Done.

C.

The Scrum Master defines and communicates the Acceptance Criteria to the Scrum Team.

D.

During the Sprint Retrospect Meeting, the Acceptance Criteria provide context for the Product Owner to decide if a User Story has been completed satisfactorily.

Question 4

As a Scrum Master, you must be familiar with the Risk Assessment Techniques that are used to assess the likelihood and impact of risks on a project. Select the inappropriate Risk Assessment Technique pairing with its salient qualities.

Options:

A.

Expected Monetary Value: Product of monetary impact and risk's probability.

B.

Pareto Analysis: Ranks risks by magnitude.

C.

Probability Impact Grid: Values of potential events are used to calculate the overall impact of risk occurrence.

D.

Probability Trees: A branch for each possible outcome of potential events is represented on a graph.

Question 5

Why are Epics decomposed into smaller, more granular User Stories during a Sprint?

Options:

A.

Tasks are easier to complete.

B.

Scrum Teams are smaller in size.

C.

They are too large to be completed in a Sprint.

D.

They take considerably longer to review.

Question 6

You are one of the Scrum Masters on a program to establish a multi-specialty hospital in Newtown. As a Scrum Master, you should be aware of the metrics used to track progress in a Sprint. Which of the following metrics indicates the number of story points delivered in a single Sprint?

Options:

A.

Velocity

B.

Business Value Delivered

C.

Number of Stories

D.

Sprint Burndown Chart

Question 7

Which of the following traits is desirable of a Scrum Team member?

Options:

A.

Scrum expertise and mastery over specialist tools and techniques

B.

Negotiation skills and product knowledge

C.

Business domain knowledge and Scrum expertise

D.

Collaborative, highly motivated, and independent

Question 8

Which of the following statements on managing risks in a Scrum project is inaccurate?

Options:

A.

The iterative nature of Scrum with its rapid turnaround time and feedback cycles allows for early detection of failures.

B.

Risks can be managed only at the project level, even if they are related to or originate in portfolios or programs.

C.

Risk Burndown Charts are an important tool for communicating information related to risks to the stakeholders.

D.

Risk is largely minimized in Scrum due to the flexibility in adding or modifying requirements at any time in the project lifecycle.

Question 9

The Project Vision Statement is a document created by the Product Owner and is an output of the Create Project Vision process. Which of the following does a Project Vision achieve?

Options:

A.

Share project status with stakeholders.

B.

Capture specific project requirements.

C.

Help monitor project progress on a daily basis.

D.

Define the objective of the project.

Question 10

Which of the following responsibilities are associated with the Scrum Master role?

I. Define the strategic objectives and priorities for projects.

II. Ensure that Scrum processes are correctly followed by all team members, including the Product Owner.

III. Ensure transparency in product development.

IV. Facilitate the Release Planning Meeting and schedule other meetings.

Options:

A.

Only II

B.

Only III and IV

C.

Only II, III, and IV

D.

Only I and II

Question 11

Which of the following is NOT a factor that differentiates the Scrum framework from the traditional project management model?

Options:

A.

Organization style in Scrum is self-organized, while in traditional models it is managed.

B.

In Scrum, the emphasis is on people, while in traditional models the emphasis is on processes.

C.

In Scrum, ROI is only achieved at the end of the project, while in traditional models ROI can be achieved throughout the project.

D.

In terms of quality, Scrum is customer-centric while traditional models are process-centric.

Question 12

The Product Owner on a project, on which you are the Scrum Master, has identified disaster situations, such as earthquakes and tsunamis, as potential risks to the underwater transnational communication sea link. The stakeholders have suggested that steps to safeguard the foundations of the ocean infrastructure be taken at the earliest and have also recommended that a contingency reserve be created, which could be used in case of disaster situations. This is an example of:

Options:

A.

Risk Mitigation

B.

Risk Prioritization

C.

Risk Avoidance

D.

Risk Assessment

Question 13

NextGen Tech has a wide range of software products in its portfolio. In which of the projects listed below is Scrum going to be very useful?

Options:

A.

Vault Safe — New, cutting-edge, unique encryption software

B.

Paint Pro — Image-editing software that often requires changes in order to stand out against competition

C.

Money Manager — Banking software being developed for a commercial bank with growing feature needs and changing security requirements

D.

All of the above

Question 14

Which of the following are the questions that are generally answered during the Scrum of Scrums Meeting?

I. What has my team been working on since the last meeting?

II. What will my team do until the next meeting?

III. What were other teams counting on our team to finish that remains undone?

IV. What is our team planning on doing that might affect other teams?

Options:

A.

III and IV

B.

I and II

C.

I, II, and IV

D.

All of the above

Question 15

The Scrum Master should ensure the following in order for the Product Owner to successfully deploy the product release as part of the Ship Deliverables process:

Options:

A.

The Scrum Team creates Deliverables as agreed upon.

B.

The Release Plan and Prioritized Product Backlog are updated.

C.

The Scrum Team creates the Release Planning Schedule.

D.

The Scrum Team accepts/rejects the deliverables during the Demonstrate and Validate Sprint process.

Question 16

What is the definition of “Accepted Deliverables” in Scrum?

Options:

A.

Those User Stories which have been completed by the Scrum Team.

B.

Those User Stories which have met the Acceptance Criteria and are accepted by the Product Owner.

C.

Those User Stories that the Scrum Team considers potentially shippable.

D.

Those User Stories which have passed the quality tests conducted by the Scrum Team.

Question 17

Which of the following statement(s) is/are true with respect to Change in Scrum projects?

I. The Scrum Master suggests changes in consultation with the Scrum Team.

II. The Scrum Master can recommend changes based on Retrospect Sprint Meetings.

III. Changes that are beyond the tolerance level of the Product Owner may need the assistance of the Scrum Master working with the Product Owner.

IV. The Scrum Master finalizes the formal Change Requests along with the Scrum Team.

Options:

A.

Only IV

B.

III and IV

C.

I and II

D.

Only I

Question 18

As defined in the SBOK Guide, which of the following is NOT a Scrum principle?

Options:

A.

Collaboration

B.

Iterative Development

C.

Manage by Stages

D.

Value-based Prioritization

Question 19

Which of the following is a process in the Initiate phase of Scrum?

Options:

A.

Identify Scrum Master and Stakeholder(s)

B.

Estimate User Stories

C.

Conduct Daily Standup

D.

Commit User Stories

Question 20

During the Ship Deliverables process, in order to deploy Product Releases and coordinate this with the customer, the Product Owner and Scrum Master plan to have a Piloting Plan. How can they make it effective?

Options:

A.

By ensuring that the target deployment user base is specified in the plan

B.

By ensuring that security-related issues are specified in the plan

C.

By ensuring that guidelines for minimizing friction among employees are specified in the plan

D.

By ensuring that synchronization methods are specified in the plan

Question 21

Damage to life and property due to floods and landslides has been identified as a potential risk on a hydroelectric power project. Which of the following Risk Assessment Techniques can the Scrum Team employ to evaluate potential risks and their impact on project objectives?

Options:

A.

Probability Impact Grid

B.

Probability Trees

C.

Pareto Analysis

D.

Expected Monetary Value

Question 22

A Scrum of Scrums Meeting is an important element when scaling Scrum to large projects. Typically, there is one representative in the meeting from each Scrum Team—usually the Scrum Master—but it is also common for other members of a Scrum Team to attend the meeting if required. Which of the following roles facilitates this meeting?

Options:

A.

Portfolio Product Owner

B.

Product Owner

C.

Chief Scrum Master

D.

Sponsor/Customer

Question 23

Clara is a Scrum Master on a project that involves offshore oil drilling. The Product Owner on her project has identified that there is a probability of getting new orders in the future, which might depend on the performance of the project. How would this risk be labelled?

Options:

A.

As a Threat

B.

As an Issue

C.

As a Weakness

D.

As an Opportunity

Question 24

Which of the following statements on the Scrum framework is CORRECT?

Options:

A.

Scrum should only be used for small projects.

B.

Scrum can only be used for software development.

C.

Scrum should only be used with teams of 6–10 people.

D.

Scrum can only be used for large corporations.

Question 25

In Scrum projects, which of the following acts as an artifact to depict the actual progress versus planned progress of a team?

Options:

A.

Scrumboard

B.

Cumulative Flow Diagram

C.

Burndown Chart

D.

Kanban Board

Question 26

Collaboration is one of the important Scrum principles. It ensures that the Scrum Core Team collaborates with each other and relevant stakeholders, thereby increasing efficiency and practicing continuous improvement. All of the following activities constitute collaboration EXCEPT:

Options:

A.

The Scrum Team decides which User Stories are important and assigns which Sprint they should be worked on.

B.

The Scrum Team discusses the best approach to creating deliverables during a Sprint.

C.

A Scrum Team member is facing difficulties in one of his tasks and another team member pitches in to help him.

D.

The Scrum Team interacts with the Product Owner to obtain clarification on User Stories.

Question 27

As a Program Scrum Master, which of the following responsibilities should you fulfill?

Options:

A.

Assess the viability of a Program by creating a Business Case for all the projects that are part of the Program

B.

Envision the objectives, outcomes, and releases of a Program

C.

Facilitate and teach Scrum practices to everyone involved in the Program

D.

Directly influence all the projects in the Program throughout the development process

Question 28

The Product Owner on a project to manufacture components for engines used in submarines received feedback from the customer after the first release that there were some defects in the product, but that the product could be released despite the defects. However, if there is an increase in the number of defects, the deliverables would be rejected. This is an example of:

Options:

A.

Risk Tolerance

B.

Risk Seeking

C.

Risk Appetite

D.

Risk Threshold

Question 29

While creating the Sprint Backlog, the Scrum Team along with the Scrum Master and Product Owner must consider which of the following as inputs?

Options:

A.

Length of Sprint, Agreed Actionable Improvements, Done Criteria, Team Calendar

B.

Assigned Action Items, Business Improvements, Dependencies, Team Calendar

C.

Length of Sprint, Previous Sprint Velocity, Dependencies, Team Calendar

D.

Proof of Concept, Previous Sprint Velocity, Done Criteria, Team Calendar

Question 30

Which of the following statements are NOT true about a Scrumboard?

I. A Scrumboard can be maintained manually on paper or a whiteboard.

II. A Scrumboard is used by the stakeholders to plan and track progress during each Sprint.

III. A Scrumboard can contain three or four columns to indicate the progress of estimated tasks for the Sprint.

IV. A Scrumboard is created during the Create Deliverables process.

Options:

A.

I and II

B.

II

C.

III and IV

D.

II and III

Page: 1 / 8
Total 100 questions