Scrum facilitates flexibility through transparency, inspection, and adaptation to ultimately achieve the most valuable business outcomes. All of the following characteristics of Scrum help in achieving flexibility, EXCEPT:
All of the following contribute to the Daily Standup, EXCEPT:
One of the responsibilities of the Scrum Master is to ensure that the Product Owner does not change the Acceptance Criteria of a committed User Story in the middle of a Sprint. In this regard, which of the following statements about Acceptance Criteria is correct?
As a Scrum Master, you must be familiar with the Risk Assessment Techniques that are used to assess the likelihood and impact of risks on a project. Select the inappropriate Risk Assessment Technique pairing with its salient qualities.
Why are Epics decomposed into smaller, more granular User Stories during a Sprint?
You are one of the Scrum Masters on a program to establish a multi-specialty hospital in Newtown. As a Scrum Master, you should be aware of the metrics used to track progress in a Sprint. Which of the following metrics indicates the number of story points delivered in a single Sprint?
Which of the following traits is desirable of a Scrum Team member?
Which of the following statements on managing risks in a Scrum project is inaccurate?
The Project Vision Statement is a document created by the Product Owner and is an output of the Create Project Vision process. Which of the following does a Project Vision achieve?
Which of the following responsibilities are associated with the Scrum Master role?
I. Define the strategic objectives and priorities for projects.
II. Ensure that Scrum processes are correctly followed by all team members, including the Product Owner.
III. Ensure transparency in product development.
IV. Facilitate the Release Planning Meeting and schedule other meetings.
Which of the following is NOT a factor that differentiates the Scrum framework from the traditional project management model?
The Product Owner on a project, on which you are the Scrum Master, has identified disaster situations, such as earthquakes and tsunamis, as potential risks to the underwater transnational communication sea link. The stakeholders have suggested that steps to safeguard the foundations of the ocean infrastructure be taken at the earliest and have also recommended that a contingency reserve be created, which could be used in case of disaster situations. This is an example of:
NextGen Tech has a wide range of software products in its portfolio. In which of the projects listed below is Scrum going to be very useful?
Which of the following are the questions that are generally answered during the Scrum of Scrums Meeting?
I. What has my team been working on since the last meeting?
II. What will my team do until the next meeting?
III. What were other teams counting on our team to finish that remains undone?
IV. What is our team planning on doing that might affect other teams?
The Scrum Master should ensure the following in order for the Product Owner to successfully deploy the product release as part of the Ship Deliverables process:
What is the definition of “Accepted Deliverables” in Scrum?
Which of the following statement(s) is/are true with respect to Change in Scrum projects?
I. The Scrum Master suggests changes in consultation with the Scrum Team.
II. The Scrum Master can recommend changes based on Retrospect Sprint Meetings.
III. Changes that are beyond the tolerance level of the Product Owner may need the assistance of the Scrum Master working with the Product Owner.
IV. The Scrum Master finalizes the formal Change Requests along with the Scrum Team.
As defined in the SBOK Guide, which of the following is NOT a Scrum principle?
Which of the following is a process in the Initiate phase of Scrum?
During the Ship Deliverables process, in order to deploy Product Releases and coordinate this with the customer, the Product Owner and Scrum Master plan to have a Piloting Plan. How can they make it effective?
Damage to life and property due to floods and landslides has been identified as a potential risk on a hydroelectric power project. Which of the following Risk Assessment Techniques can the Scrum Team employ to evaluate potential risks and their impact on project objectives?
A Scrum of Scrums Meeting is an important element when scaling Scrum to large projects. Typically, there is one representative in the meeting from each Scrum Team—usually the Scrum Master—but it is also common for other members of a Scrum Team to attend the meeting if required. Which of the following roles facilitates this meeting?
Clara is a Scrum Master on a project that involves offshore oil drilling. The Product Owner on her project has identified that there is a probability of getting new orders in the future, which might depend on the performance of the project. How would this risk be labelled?
Which of the following statements on the Scrum framework is CORRECT?
In Scrum projects, which of the following acts as an artifact to depict the actual progress versus planned progress of a team?
Collaboration is one of the important Scrum principles. It ensures that the Scrum Core Team collaborates with each other and relevant stakeholders, thereby increasing efficiency and practicing continuous improvement. All of the following activities constitute collaboration EXCEPT:
As a Program Scrum Master, which of the following responsibilities should you fulfill?
The Product Owner on a project to manufacture components for engines used in submarines received feedback from the customer after the first release that there were some defects in the product, but that the product could be released despite the defects. However, if there is an increase in the number of defects, the deliverables would be rejected. This is an example of:
While creating the Sprint Backlog, the Scrum Team along with the Scrum Master and Product Owner must consider which of the following as inputs?
Which of the following statements are NOT true about a Scrumboard?
I. A Scrumboard can be maintained manually on paper or a whiteboard.
II. A Scrumboard is used by the stakeholders to plan and track progress during each Sprint.
III. A Scrumboard can contain three or four columns to indicate the progress of estimated tasks for the Sprint.
IV. A Scrumboard is created during the Create Deliverables process.