Question 29

While creating the Sprint Backlog, the Scrum Team along with the Scrum Master and Product Owner must consider which of the following as inputs?

Options:

A.

Length of Sprint, Agreed Actionable Improvements, Done Criteria, Team Calendar

B.

Assigned Action Items, Business Improvements, Dependencies, Team Calendar

C.

Length of Sprint, Previous Sprint Velocity, Dependencies, Team Calendar

D.

Proof of Concept, Previous Sprint Velocity, Done Criteria, Team Calendar

Question 30

Which of the following statements are NOT true about a Scrumboard?

I. A Scrumboard can be maintained manually on paper or a whiteboard.

II. A Scrumboard is used by the stakeholders to plan and track progress during each Sprint.

III. A Scrumboard can contain three or four columns to indicate the progress of estimated tasks for the Sprint.

IV. A Scrumboard is created during the Create Deliverables process.

Options:

A.

I and II

B.

II

C.

III and IV

D.

II and III

Page: 8 / 8